Off-plan projects in Dubai World Central

53 projects in Dubai World Central are under construction. On average they are 31% built. 10 have passed their registered completion date. The next one due is Fairway Villas 2, in December 2026.

Questions

How many off-plan projects are under construction in Dubai World Central?

53 projects are under construction in Dubai World Central, 31% built on average at the latest site inspections.

Which Dubai World Central projects are due to finish next?

By registered completion date: Fairway Villas 2 (December 2026, 92% built), Azizi Venice 15 (May 2027, 3.3% built) and Azizi Venice 16 (June 2027, 3.7% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.

How many Dubai World Central projects are past their completion date?

10 of 53, among them Discovery Dunes, Azizi Venice 5 and Azizi Venice 3. A project counts as late once its registered completion date has passed before it reaches 100%.

Which developers are building in Dubai World Central?

The developers with the most projects here are Emaar Dubai South Dwc (18), Azizi Developments (16) and Bt Properties Dwc (5), out of 12 building in Dubai World Central.

Reading these figures

Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.

What happens at handover and how to snag a new home cover the steps after 100%.

Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.