Expo City Valley construction progress
Expo City Valley in Dubai World Central is 66% built at the Land Department inspection of August 2026. Developer Expo City Valley Development Fzco. Completion registered for January 2026.
66%
Built, at the Land Department site inspection of 19 August 2026
8 months past its registered completion date
- Completion date (Land Department)
- January 2026
- Finish at recent pace
- June 2027
- Construction started
- May 2023
- Registered with the Land Department
- April 2023
- Developer
- Expo City Valley Development Fzco
- Community
- Dubai World Central
- Units
- 489
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- إكسبو سيتي فالي
- Land Department project number
- 2623
- Land Department site inspections
- 7
Schedule
Expo City Valley was registered to complete in January 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
19 August 2026
66%+14 pts
1 May 2026
52%+10 pts
24 December 2025
42%+18 pts
22 August 2025
24%+15 pts
12 March 2025
8.3%+7.9 pts
11 December 2023
0.4%+0.4 pts
27 April 2023
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Own a unit in Expo City Valley?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Expo City Valley be completed?
- The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Expo City Valley is built?
- 66%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since April 2023.
- Is Expo City Valley delayed?
- Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
- Who is building Expo City Valley?
- The registered developer is Expo City Valley Development Fzco.
- Which bank holds the escrow account for Expo City Valley?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Azizi Venice 4Nearby in Dubai World Central. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)