Skip to content

Golf Hills construction progress

The registered completion date for Golf Hills in Dubai World Central is September 2029. At the last site inspection, in June 2026, it was 3.7% built. The developer is Emaar Dubai South Dwc.

3.7%

Built, at the site inspection of 23 June 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
January 2046
Construction started
December 2025
First registered
October 2025
Units
204
Escrow bank
First Abu Dhabi Bank
Name in Arabic
جولف هيلز
Project number
4117
Site inspections
3

Schedule

Between September 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around January 2046, more than three months after its registered date of September 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 June 2026

3.7%+3.4 pts

  • Golf Hills construction site, inspection photo 1, 23 June 2026
  • Golf Hills construction site, inspection photo 2, 23 June 2026
  • Golf Hills construction site, inspection photo 3, 23 June 2026

13 March 2026

0.2%+0.2 pts

  • Golf Hills construction site, inspection photo 1, 13 March 2026
  • Golf Hills construction site, inspection photo 2, 13 March 2026
  • Golf Hills construction site, inspection photo 3, 13 March 2026

24 September 2025

0%

  • Golf Hills construction site, inspection photo 1, 24 September 2025
  • Golf Hills construction site, inspection photo 2, 24 September 2025

All 8 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Hills handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2046. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Hills?
Golf Hills was 3.7% built at the site inspection on 23 June 2026. The site has been inspected 3 times since September 2025. The Land Department took 8 site photos at its inspections.
Is Golf Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Golf Hills?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Hills?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.