Skip to content

Golf Hills construction progress

Golf Hills in Dubai World Central is 3.7% built at the Land Department inspection of June 2026. Developer Emaar Dubai South Dwc. Completion registered for September 2029.

3.7%

Built, at the Land Department site inspection of 23 June 2026

Running behind its date

Completion date (Land Department)
September 2029
Finish at recent pace
January 2046
Construction started
December 2025
Registered with the Land Department
October 2025
Units
204
Escrow bank
First Abu Dhabi Bank
Name in Arabic
جولف هيلز
Land Department project number
4117
Land Department site inspections
3

Schedule

Between September 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around January 2046, more than three months after the September 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

3.7%+3.4 pts

  • Golf Hills construction site, Land Department inspection photo 1, 23 June 2026
  • Golf Hills construction site, Land Department inspection photo 2, 23 June 2026
  • Golf Hills construction site, Land Department inspection photo 3, 23 June 2026

13 March 2026

0.2%+0.2 pts

  • Golf Hills construction site, Land Department inspection photo 1, 13 March 2026
  • Golf Hills construction site, Land Department inspection photo 2, 13 March 2026
  • Golf Hills construction site, Land Department inspection photo 3, 13 March 2026

24 September 2025

0%

  • Golf Hills construction site, Land Department inspection photo 1, 24 September 2025
  • Golf Hills construction site, Land Department inspection photo 2, 24 September 2025

All 8 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Hills?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Golf Hills be completed?
The completion date registered with the Dubai Land Department is September 2029. At the pace of its recent inspections the site would reach 100% around January 2046. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Golf Hills is built?
3.7%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Golf Hills delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Golf Hills?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Hills?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.