Waada - Altura 2 construction progress

Waada - Altura 2 in Dubai World Central is 4.1% built at the Land Department inspection of April 2026. Developer Bt Properties Dwc. Completion registered for March 2029.

4.1%

Built, at the Land Department site inspection of 13 April 2026

Running behind its date

Completion date (Land Department)
March 2029
Finish at recent pace
March 2039
Construction started
March 2026
Registered with the Land Department
October 2025
Units
365
Escrow bank
The National Bank of Fujairah
Name in Arabic
وعد - الطور 2
Land Department project number
4085
Land Department site inspections
2

Schedule

Between September 2025 and April 2026 the site added about 0.6 points a month. At that rate it would finish around March 2039, more than three months after the March 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 April 2026

4.1%+4.1 pts

  • Waada - Altura 2 construction site, Land Department inspection photo 1, 13 April 2026
  • Waada - Altura 2 construction site, Land Department inspection photo 2, 13 April 2026

25 September 2025

0%

  • Waada - Altura 2 construction site, Land Department inspection photo 1, 25 September 2025
  • Waada - Altura 2 construction site, Land Department inspection photo 2, 25 September 2025

All 4 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average. Waada - Altura 2 is behind that average.

Bt Properties Dwc has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Waada - Altura 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Waada - Altura 2 be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around March 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Waada - Altura 2 is built?
4.1%, measured at the Land Department site inspection on 13 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Waada - Altura 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Waada - Altura 2?
The registered developer is Bt Properties Dwc. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Waada - Altura 2?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.