Expo City Al Waha Residences 01 construction progress

Expo City Al Waha Residences 01 in Dubai World Central is 66% built at the Land Department inspection of August 2026. Developer Expo City Al Waha Residences Development Fzco. Completion registered for June 2027.

66%

Built, at the Land Department site inspection of 26 August 2026

On pace for its date

Completion date (Land Department)
June 2027
Finish at recent pace
August 2027
Construction started
May 2025
Registered with the Land Department
February 2025
Developer
Expo City Al Waha Residences Development Fzco
Units
288
Escrow bank
Emirates NBD
Name in Arabic
إكسبو سيتي الواحة ريزيدنسز 01
Land Department project number
3523
Land Department site inspections
3

Schedule

Since April 2026 Expo City Al Waha Residences 01 has added about 3.0 points a month. That puts 100% around August 2027, within three months of its registered completion date of June 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

26 August 2026

66%+12 pts

  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 1, 26 August 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 2, 26 August 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 3, 26 August 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 4, 26 August 2026

20 April 2026

53%+6.6 pts

  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 1, 20 April 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 2, 20 April 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 3, 20 April 2026
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 4, 20 April 2026

19 May 2025

47%

  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 1, 19 May 2025
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 2, 19 May 2025
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 3, 19 May 2025
  • Expo City Al Waha Residences 01 construction site, Land Department inspection photo 4, 19 May 2025

All 22 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Expo City Al Waha Residences Development Fzco has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Expo City Al Waha Residences 01?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Expo City Al Waha Residences 01 be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Expo City Al Waha Residences 01 is built?
66%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Expo City Al Waha Residences 01 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of June 2027.
Who is building Expo City Al Waha Residences 01?
The registered developer is Expo City Al Waha Residences Development Fzco. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Expo City Al Waha Residences 01?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.