South Square construction progress

The registered completion date for South Square in Dubai World Central is June 2028. At the last site inspection, in June 2026, it was 2.6% built. The developer is Dubai South Properties Dwc.

2.6%

Built, at the site inspection of 17 June 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
February 2069
Construction started
October 2025
First registered
May 2025
Units
571
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ساوث سكوير
Project number
3711
Site inspections
2

Schedule

Between April 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around February 2069, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 June 2026

2.6%+2.6 pts

  • South Square construction site, inspection photo 1, 17 June 2026
  • South Square construction site, inspection photo 2, 17 June 2026
  • South Square construction site, inspection photo 3, 17 June 2026
  • South Square construction site, inspection photo 4, 17 June 2026

24 April 2025

0%

  • South Square construction site, inspection photo 1, 24 April 2025
  • South Square construction site, inspection photo 2, 24 April 2025

All 7 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in South Square?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the South Square handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2069. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on South Square?
South Square was 2.6% built at the site inspection on 17 June 2026. The site has been inspected 2 times since April 2025. The Land Department took 7 site photos at its inspections.
Is South Square delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building South Square?
The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for South Square?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.