Azizi Venice 3 construction progress

Azizi Venice 3 in Dubai World Central was registered to complete in December 2025 and is still under construction. At the last site inspection, in June 2026, it was 76% built. The developer is Azizi Developments.

76%

Built, at the site inspection of 15 June 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
May 2028
Construction started
September 2023
First registered
October 2023
Units
352
Escrow bank
Emirates NBD
Name in Arabic
عزيزى فينيس 3
Project number
2799
Site inspections
3

Schedule

Azizi Venice 3 was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around May 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 June 2026

76%+5.6 pts

  • Azizi Venice 3 construction site, inspection photo 1, 15 June 2026
  • Azizi Venice 3 construction site, inspection photo 2, 15 June 2026

6 January 2026

70%+40 pts

  • Azizi Venice 3 construction site, inspection photo 1, 6 January 2026
  • Azizi Venice 3 construction site, inspection photo 2, 6 January 2026
  • Azizi Venice 3 construction site, inspection photo 3, 6 January 2026
  • Azizi Venice 3 construction site, inspection photo 4, 6 January 2026

10 September 2024

30%

  • Azizi Venice 3 construction site, inspection photo 1, 10 September 2024
  • Azizi Venice 3 construction site, inspection photo 2, 10 September 2024
  • Azizi Venice 3 construction site, inspection photo 3, 10 September 2024
  • Azizi Venice 3 construction site, inspection photo 4, 10 September 2024

All 17 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 3 handover date?
The registered completion date was December 2025, and the register still lists Azizi Venice 3 as under construction. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 3?
Azizi Venice 3 was 76% built at the site inspection on 15 June 2026. The site has been inspected 3 times since September 2024. The Land Department took 17 site photos at its inspections.
Is Azizi Venice 3 delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Azizi Venice 3?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.