Skip to content

Greenspoint 2 construction progress

Greenspoint 2 in Dubai World Central is 40% built at the Land Department inspection of August 2026. Developer Emaar Dubai South Dwc. Completion registered for March 2029.

40%

Built, at the Land Department site inspection of 3 August 2026

On pace for its date

Completion date (Land Department)
March 2029
Finish at recent pace
December 2027
Construction started
January 2025
Registered with the Land Department
February 2025
Units
244
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جرينز بوينت 2
Land Department project number
3558
Land Department site inspections
4

Schedule

Since November 2025 Greenspoint 2 has added about 3.7 points a month. That puts 100% around December 2027, within three months of its registered completion date of March 2029.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

40%+20 pts

  • Greenspoint 2 construction site, Land Department inspection photo 1, 3 August 2026
  • Greenspoint 2 construction site, Land Department inspection photo 2, 3 August 2026
  • Greenspoint 2 construction site, Land Department inspection photo 3, 3 August 2026
  • Greenspoint 2 construction site, Land Department inspection photo 4, 3 August 2026

21 April 2026

20%+11 pts

  • Greenspoint 2 construction site, Land Department inspection photo 1, 21 April 2026
  • Greenspoint 2 construction site, Land Department inspection photo 2, 21 April 2026
  • Greenspoint 2 construction site, Land Department inspection photo 3, 21 April 2026
  • Greenspoint 2 construction site, Land Department inspection photo 4, 21 April 2026

27 November 2025

9.6%+9.6 pts

  • Greenspoint 2 construction site, Land Department inspection photo 1, 27 November 2025
  • Greenspoint 2 construction site, Land Department inspection photo 2, 27 November 2025
  • Greenspoint 2 construction site, Land Department inspection photo 3, 27 November 2025
  • Greenspoint 2 construction site, Land Department inspection photo 4, 27 November 2025

11 February 2025

0%

  • Greenspoint 2 construction site, Land Department inspection photo 1, 11 February 2025
  • Greenspoint 2 construction site, Land Department inspection photo 2, 11 February 2025

All 24 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenspoint 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Greenspoint 2 be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Greenspoint 2 is built?
40%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Greenspoint 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
Who is building Greenspoint 2?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Greenspoint 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.