Golf Lane construction progress

No completion date is registered for Golf Lane in Dubai World Central yet. At the last site inspection, in November 2026, it was 57% built. The developer is Emaar Dubai South Dwc.

57%

Built, at the site inspection of 12 November 2026

Finish at recent pace
November 2027
Construction started
October 2024
First registered
May 2024
Units
574
Escrow bank
Dubai Islamic Bank
Name in Arabic
جولف لاين
Project number
3111
Site inspections
8

Schedule

Since February 2026 Golf Lane has added about 3.7 points a month. At that rate the site reaches 100% around November 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

12 November 2026

57%+26 pts

  • Golf Lane construction site, inspection photo 1, 12 November 2026
  • Golf Lane construction site, inspection photo 2, 12 November 2026
  • Golf Lane construction site, inspection photo 3, 12 November 2026
  • Golf Lane construction site, inspection photo 4, 12 November 2026

18 June 2026

30%+6.5 pts

  • Golf Lane construction site, inspection photo 1, 18 June 2026
  • Golf Lane construction site, inspection photo 2, 18 June 2026
  • Golf Lane construction site, inspection photo 3, 18 June 2026
  • Golf Lane construction site, inspection photo 4, 18 June 2026

16 February 2026

24%+11 pts

  • Golf Lane construction site, inspection photo 1, 16 February 2026
  • Golf Lane construction site, inspection photo 2, 16 February 2026
  • Golf Lane construction site, inspection photo 3, 16 February 2026
  • Golf Lane construction site, inspection photo 4, 16 February 2026

31 October 2025

13%+6.4 pts

  • Golf Lane construction site, inspection photo 1, 31 October 2025
  • Golf Lane construction site, inspection photo 2, 31 October 2025
  • Golf Lane construction site, inspection photo 3, 31 October 2025
  • Golf Lane construction site, inspection photo 4, 31 October 2025

21 July 2025

6.4%+3.6 pts

  • Golf Lane construction site, inspection photo 1, 21 July 2025
  • Golf Lane construction site, inspection photo 2, 21 July 2025
  • Golf Lane construction site, inspection photo 3, 21 July 2025
  • Golf Lane construction site, inspection photo 4, 21 July 2025

14 April 2025

2.8%+2.5 pts

  • Golf Lane construction site, inspection photo 1, 14 April 2025
  • Golf Lane construction site, inspection photo 2, 14 April 2025
  • Golf Lane construction site, inspection photo 3, 14 April 2025
  • Golf Lane construction site, inspection photo 4, 14 April 2025

5 December 2024

0.2%+0.2 pts

  • Golf Lane construction site, inspection photo 1, 5 December 2024
  • Golf Lane construction site, inspection photo 2, 5 December 2024
  • Golf Lane construction site, inspection photo 3, 5 December 2024

28 May 2024

0%

  • Golf Lane construction site, inspection photo 1, 28 May 2024
  • Golf Lane construction site, inspection photo 2, 28 May 2024
  • Golf Lane construction site, inspection photo 3, 28 May 2024

All 71 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Lane?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Lane handover date?
No completion date is on record for Golf Lane yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Golf Lane?
Golf Lane was 57% built at the site inspection on 12 November 2026. The site has been inspected 8 times since May 2024. The Land Department took 71 site photos at its inspections.
Who is building Golf Lane?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Lane?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.