Azizi Venice 13 construction progress
The registered completion date for Azizi Venice 13 in Dubai World Central is September 2027. At the last site inspection, in October 2026, it was 46% built. The developer is Azizi Developments.
46%
Built, at the site inspection of 14 October 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- March 2029
- Construction started
- September 2024
- First registered
- October 2024
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 1,888
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- عزيزي فينيس 13
- Project number
- 3297
- Site inspections
- 5
Schedule
Between December 2025 and October 2026 the site added about 1.9 points a month. At that rate it would finish around March 2029, more than three months after its registered date of September 2027.
Site inspections
14 October 2026
46%+5.5 pts
22 April 2026
40%+13 pts
9 December 2025
27%+11 pts
9 July 2025
16%+16 pts
27 September 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Venice 13?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Venice 13 handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Venice 13?
- Azizi Venice 13 was 46% built at the site inspection on 14 October 2026. The site has been inspected 5 times since September 2024. The Land Department took 41 site photos at its inspections.
- Is Azizi Venice 13 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Azizi Venice 13?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 13?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)









