Hayat 4 construction progress
The registered completion date for Hayat 4 in Dubai World Central is July 2028. At the last site inspection, in September 2026, it was 4.5% built. The developer is Dubai South Properties Dwc.
4.5%
Built, at the site inspection of 24 September 2026
Running behind its date
- Registered completion date
- July 2028
- Finish at recent pace
- April 2037
- Construction started
- March 2026
- First registered
- September 2025
- Developer
- Dubai South Properties Dwc
- Community
- Dubai World Central
- Units
- 200
- Escrow bank
- Emirates NBD
- Name in Arabic
- حياة 4
- Project number
- 4038
- Site inspections
- 3
Schedule
Between March 2026 and September 2026 the site added about 0.8 points a month. At that rate it would finish around April 2037, more than three months after its registered date of July 2028.
Site inspections
24 September 2026
4.5%+4.5 pts
26 March 2026
0%
21 August 2025
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Hayat 4?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Hayat 4 handover date?
- The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Hayat 4?
- Hayat 4 was 4.5% built at the site inspection on 24 September 2026. The site has been inspected 3 times since August 2025. The Land Department took 8 site photos at its inspections.
- Is Hayat 4 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2028.
- Who is building Hayat 4?
- The registered developer is Dubai South Properties Dwc. It has 18 other projects under construction in Dubai.
- Which bank holds the escrow account for Hayat 4?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Bay 1Also by Dubai South Properties Dwc. 94%, Due March 2025, passed.
- South Bay 2Also by Dubai South Properties Dwc. 94%, Due May 2026, passed.
- South Bay 3 PremiumAlso by Dubai South Properties Dwc. 88%.
- South Bay 4 PremiumAlso by Dubai South Properties Dwc. 86%.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.