Azizi Venice 1 construction progress
Azizi Venice 1 in Dubai World Central was registered to complete in December 2025 and is still under construction. At the last site inspection, in May 2026, it was 67% built. The developer is Azizi Developments.
67%
Built, at the site inspection of 13 May 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- February 2028
- Construction started
- October 2023
- First registered
- November 2023
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 143
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- عزيزى فينيس 1
- Project number
- 2821
- Site inspections
- 6
Schedule
Azizi Venice 1 was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
13 May 2026
67%+6.3 pts
29 January 2026
61%+8.6 pts
21 July 2025
52%+4.0 pts
10 April 2025
48%+25 pts
10 September 2024
23%+23 pts
25 October 2023
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Venice 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Venice 1 handover date?
- The registered completion date was December 2025, and the register still lists Azizi Venice 1 as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Venice 1?
- Azizi Venice 1 was 67% built at the site inspection on 13 May 2026. The site has been inspected 6 times since October 2023. The Land Department took 39 site photos at its inspections.
- Is Azizi Venice 1 delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Azizi Venice 1?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 1?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.