Azizi Venice 1 construction progress
Azizi Venice 1 in Dubai World Central is 67% built at the Land Department inspection of May 2026. Developer Azizi Developments. Completion registered for December 2025.
67%
Built, at the Land Department site inspection of 13 May 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- February 2028
- Construction started
- October 2023
- Registered with the Land Department
- November 2023
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 143
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- عزيزى فينيس 1
- Land Department project number
- 2821
- Land Department site inspections
- 6
Schedule
Azizi Venice 1 was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
13 May 2026
67%+6.3 pts
29 January 2026
61%+8.6 pts
21 July 2025
52%+4.0 pts
10 April 2025
48%+25 pts
10 September 2024
23%+23 pts
25 October 2023
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Venice 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Venice 1 be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Venice 1 is built?
- 67%, measured at the Land Department site inspection on 13 May 2026. The Land Department engineers have inspected the site 6 times since October 2023.
- Is Azizi Venice 1 delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Azizi Venice 1?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 1?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Fairway Villas 3Nearby in Dubai World Central. 49%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)