Azizi Venice 6 construction progress

The registered completion date for Azizi Venice 6 in Dubai World Central is December 2027. At the last site inspection, in May 2026, it was 12% built. The developer is Azizi Developments.

27%

Built, at the site inspection of 8 May 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
December 2036
Construction started
December 2024
First registered
January 2025
Units
2,965
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي فينيس 6
Project number
3474
Site inspections
3

Schedule

Between December 2025 and May 2026 the site added about 0.7 points a month. At that rate it would finish around December 2036, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 May 2026

12%+3.4 pts

  • Azizi Venice 6 construction site, inspection photo 1, 8 May 2026
  • Azizi Venice 6 construction site, inspection photo 2, 8 May 2026
  • Azizi Venice 6 construction site, inspection photo 3, 8 May 2026
  • Azizi Venice 6 construction site, inspection photo 4, 8 May 2026

9 December 2025

8.2%+8.2 pts

  • Azizi Venice 6 construction site, inspection photo 1, 9 December 2025
  • Azizi Venice 6 construction site, inspection photo 2, 9 December 2025
  • Azizi Venice 6 construction site, inspection photo 3, 9 December 2025
  • Azizi Venice 6 construction site, inspection photo 4, 9 December 2025

26 December 2024

0%

  • Azizi Venice 6 construction site, inspection photo 1, 26 December 2024
  • Azizi Venice 6 construction site, inspection photo 2, 26 December 2024

All 12 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 6?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 6 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 6?
Azizi Venice 6 was 27% built at the site inspection on 8 May 2026. The site has been inspected 3 times since December 2024. The Land Department took 12 site photos at its inspections.
Is Azizi Venice 6 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Azizi Venice 6?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 6?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.