Azizi Venice 6 construction progress

Azizi Venice 6 in Dubai World Central is 12% built at the Land Department inspection of May 2026. Developer Azizi Developments. Completion registered for December 2027.

12%

Built, at the Land Department site inspection of 8 May 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
December 2036
Construction started
December 2024
Registered with the Land Department
January 2025
Units
2,965
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي فينيس 6
Land Department project number
3474
Land Department site inspections
3

Schedule

Between December 2025 and May 2026 the site added about 0.7 points a month. At that rate it would finish around December 2036, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 May 2026

12%+3.4 pts

  • Azizi Venice 6 construction site, Land Department inspection photo 1, 8 May 2026
  • Azizi Venice 6 construction site, Land Department inspection photo 2, 8 May 2026
  • Azizi Venice 6 construction site, Land Department inspection photo 3, 8 May 2026
  • Azizi Venice 6 construction site, Land Department inspection photo 4, 8 May 2026

9 December 2025

8.2%+8.2 pts

  • Azizi Venice 6 construction site, Land Department inspection photo 1, 9 December 2025
  • Azizi Venice 6 construction site, Land Department inspection photo 2, 9 December 2025
  • Azizi Venice 6 construction site, Land Department inspection photo 3, 9 December 2025
  • Azizi Venice 6 construction site, Land Department inspection photo 4, 9 December 2025

26 December 2024

0%

  • Azizi Venice 6 construction site, Land Department inspection photo 1, 26 December 2024
  • Azizi Venice 6 construction site, Land Department inspection photo 2, 26 December 2024

All 12 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Venice 6?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Venice 6 be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around December 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Venice 6 is built?
12%, measured at the Land Department site inspection on 8 May 2026. The Land Department engineers have inspected the site 3 times since December 2024.
Is Azizi Venice 6 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Azizi Venice 6?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 6?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.