Greenville 2 construction progress
Greenville 2 in Dubai World Central is 47% built at the Land Department inspection of July 2026. Developer Emaar Dubai South Dwc. Completion registered for March 2029.
47%
Built, at the Land Department site inspection of 19 July 2026
On pace for its date
- Completion date (Land Department)
- March 2029
- Finish at recent pace
- August 2027
- Construction started
- January 2025
- Registered with the Land Department
- October 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 148
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- جرينفل 2
- Land Department project number
- 3319
- Land Department site inspections
- 6
Schedule
Since September 2025 Greenville 2 has added about 4.0 points a month. That puts 100% around August 2027, within three months of its registered completion date of March 2029.
Site inspections
19 July 2026
47%+16 pts
30 March 2026
31%+12 pts
31 December 2025
20%+13 pts
11 September 2025
6.4%+5.8 pts
13 May 2025
0.6%+0.6 pts
27 September 2024
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenville 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Greenville 2 be completed?
- The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Greenville 2 is built?
- 47%, measured at the Land Department site inspection on 19 July 2026. The Land Department engineers have inspected the site 6 times since September 2024.
- Is Greenville 2 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
- Who is building Greenville 2?
- The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenville 2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 30%.
- Greenway 2Also by Emaar Dubai South Dwc. 34%, Due May 2028.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)












.jpeg&w=3840&q=75)