Terra Heights construction progress
The registered completion date for Terra Heights in Dubai World Central is March 2029. At the last site inspection, in July 2026, it was 9.1% built. The developer is Dwtc Emaar.
9.1%
Built, at the site inspection of 31 July 2026
Running behind its date
- Registered completion date
- March 2029
- Finish at recent pace
- September 2036
- Construction started
- April 2025
- First registered
- November 2024
- Developer
- Dwtc Emaar
- Community
- Dubai World Central
- Units
- 1,004
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- تيرا هايتس
- Project number
- 3381
- Site inspections
- 5
Schedule
Between September 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around September 2036, more than three months after its registered date of March 2029.
Site inspections
31 July 2026
9.1%+5.8 pts
21 April 2026
3.4%+2.3 pts
7 September 2025
1.1%+1.1 pts
23 May 2025
0%
6 November 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Dwtc Emaar has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Terra Heights?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Terra Heights handover date?
- The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Terra Heights?
- Terra Heights was 9.1% built at the site inspection on 31 July 2026. The site has been inspected 5 times since November 2024. The Land Department took 17 site photos at its inspections.
- Is Terra Heights delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
- Who is building Terra Heights?
- The registered developer is Dwtc Emaar. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Terra Heights?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Terra GardensAlso by Dwtc Emaar. 3.6%, Due October 2029.
- Terra WoodsAlso by Dwtc Emaar. 0%, Due March 2030.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.