Azizi Venice 10 construction progress

Azizi Venice 10 in Dubai World Central is 36% built at the Land Department inspection of May 2026. Developer Azizi Developments.

36%

Built, at the Land Department site inspection of 5 May 2026

Finish at recent pace
June 2030
Construction started
January 2024
Registered with the Land Department
February 2024
Units
1,264
Escrow bank
Mashreq Bank
Name in Arabic
عزيزى فينيس 10
Land Department project number
2955
Land Department site inspections
3

Schedule

Since January 2026 Azizi Venice 10 has added about 1.3 points a month. At that rate the site reaches 100% around June 2030. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

5 May 2026

36%+5.0 pts

  • Azizi Venice 10 construction site, Land Department inspection photo 1, 5 May 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 2, 5 May 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 3, 5 May 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 4, 5 May 2026

6 January 2026

31%+31 pts

  • Azizi Venice 10 construction site, Land Department inspection photo 1, 6 January 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 2, 6 January 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 3, 6 January 2026
  • Azizi Venice 10 construction site, Land Department inspection photo 4, 6 January 2026

29 January 2024

0%

  • Azizi Venice 10 construction site, Land Department inspection photo 1, 29 January 2024
  • Azizi Venice 10 construction site, Land Department inspection photo 2, 29 January 2024

All 20 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Venice 10?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Venice 10 be completed?
The Land Department has no completion date on record for Azizi Venice 10 yet.
How much of Azizi Venice 10 is built?
36%, measured at the Land Department site inspection on 5 May 2026. The Land Department engineers have inspected the site 3 times since January 2024.
Who is building Azizi Venice 10?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 10?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.