Azizi Venice 10 construction progress

No completion date is registered for Azizi Venice 10 in Dubai World Central yet. At the last site inspection, in May 2026, it was 36% built. The developer is Azizi Developments.

36%

Built, at the site inspection of 5 May 2026

Finish at recent pace
June 2030
Construction started
January 2024
First registered
February 2024
Units
1,264
Escrow bank
Mashreq Bank
Name in Arabic
عزيزى فينيس 10
Project number
2955
Site inspections
3

Schedule

Since January 2026 Azizi Venice 10 has added about 1.3 points a month. At that rate the site reaches 100% around June 2030. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

5 May 2026

36%+5.0 pts

  • Azizi Venice 10 construction site, inspection photo 1, 5 May 2026
  • Azizi Venice 10 construction site, inspection photo 2, 5 May 2026
  • Azizi Venice 10 construction site, inspection photo 3, 5 May 2026
  • Azizi Venice 10 construction site, inspection photo 4, 5 May 2026

6 January 2026

31%+31 pts

  • Azizi Venice 10 construction site, inspection photo 1, 6 January 2026
  • Azizi Venice 10 construction site, inspection photo 2, 6 January 2026
  • Azizi Venice 10 construction site, inspection photo 3, 6 January 2026
  • Azizi Venice 10 construction site, inspection photo 4, 6 January 2026

29 January 2024

0%

  • Azizi Venice 10 construction site, inspection photo 1, 29 January 2024
  • Azizi Venice 10 construction site, inspection photo 2, 29 January 2024

All 20 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 10?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 10 handover date?
No completion date is on record for Azizi Venice 10 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Azizi Venice 10?
Azizi Venice 10 was 36% built at the site inspection on 5 May 2026. The site has been inspected 3 times since January 2024. The Land Department took 20 site photos at its inspections.
Who is building Azizi Venice 10?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 10?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.