Azizi Venice 10 construction progress
Azizi Venice 10 in Dubai World Central is 36% built at the Land Department inspection of May 2026. Developer Azizi Developments.
36%
Built, at the Land Department site inspection of 5 May 2026
- Finish at recent pace
- June 2030
- Construction started
- January 2024
- Registered with the Land Department
- February 2024
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 1,264
- Escrow bank
- Mashreq Bank
- Name in Arabic
- عزيزى فينيس 10
- Land Department project number
- 2955
- Land Department site inspections
- 3
Schedule
Since January 2026 Azizi Venice 10 has added about 1.3 points a month. At that rate the site reaches 100% around June 2030. The Land Department has no completion date on record to compare it with.
Site inspections
5 May 2026
36%+5.0 pts
6 January 2026
31%+31 pts
29 January 2024
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Venice 10?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Venice 10 be completed?
- The Land Department has no completion date on record for Azizi Venice 10 yet.
- How much of Azizi Venice 10 is built?
- 36%, measured at the Land Department site inspection on 5 May 2026. The Land Department engineers have inspected the site 3 times since January 2024.
- Who is building Azizi Venice 10?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 10?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Fairway Villas 3Nearby in Dubai World Central. 49%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.