Azizi Venice 14 construction progress
Azizi Venice 14 in Dubai World Central is 30% built at the Land Department inspection of June 2026. Developer Azizi Developments. Completion registered for May 2026.
30%
Built, at the Land Department site inspection of 22 June 2026
5 months past its registered completion date
- Completion date (Land Department)
- May 2026
- Finish at recent pace
- January 2029
- Construction started
- May 2024
- Registered with the Land Department
- July 2024
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 3,438
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- عزيزى فينيس 14
- Land Department project number
- 3073
- Land Department site inspections
- 4
Schedule
Azizi Venice 14 was registered to complete in May 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around January 2029.
Site inspections
22 June 2026
30%+16 pts
14 November 2025
14%+4.9 pts
20 June 2025
8.9%+8.9 pts
6 May 2024
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Venice 14?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Venice 14 be completed?
- The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around January 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Venice 14 is built?
- 30%, measured at the Land Department site inspection on 22 June 2026. The Land Department engineers have inspected the site 4 times since May 2024.
- Is Azizi Venice 14 delayed?
- Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
- Who is building Azizi Venice 14?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 14?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Fairway Villas 3Nearby in Dubai World Central. 49%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.













