Azizi Venice 14 construction progress

Azizi Venice 14 in Dubai World Central was registered to complete in May 2026 and is still under construction. At the last site inspection, in June 2026, it was 30% built. The developer is Azizi Developments.

30%

Built, at the site inspection of 22 June 2026

6 months past its registered completion date

Registered completion date
May 2026
Finish at recent pace
January 2029
Construction started
May 2024
First registered
July 2024
Units
3,438
Escrow bank
First Abu Dhabi Bank
Name in Arabic
عزيزى فينيس 14
Project number
3073
Site inspections
4

Schedule

Azizi Venice 14 was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around January 2029.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 June 2026

30%+16 pts

  • Azizi Venice 14 construction site, inspection photo 1, 22 June 2026
  • Azizi Venice 14 construction site, inspection photo 2, 22 June 2026
  • Azizi Venice 14 construction site, inspection photo 3, 22 June 2026
  • Azizi Venice 14 construction site, inspection photo 4, 22 June 2026

14 November 2025

14%+4.9 pts

  • Azizi Venice 14 construction site, inspection photo 1, 14 November 2025
  • Azizi Venice 14 construction site, inspection photo 2, 14 November 2025
  • Azizi Venice 14 construction site, inspection photo 3, 14 November 2025
  • Azizi Venice 14 construction site, inspection photo 4, 14 November 2025

20 June 2025

8.9%+8.9 pts

  • Azizi Venice 14 construction site, inspection photo 1, 20 June 2025
  • Azizi Venice 14 construction site, inspection photo 2, 20 June 2025
  • Azizi Venice 14 construction site, inspection photo 3, 20 June 2025
  • Azizi Venice 14 construction site, inspection photo 4, 20 June 2025

6 May 2024

0%

  • Azizi Venice 14 construction site, inspection photo 1, 6 May 2024
  • Azizi Venice 14 construction site, inspection photo 2, 6 May 2024

All 21 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 14?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 14 handover date?
The registered completion date was May 2026, and the register still lists Azizi Venice 14 as under construction. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 14?
Azizi Venice 14 was 30% built at the site inspection on 22 June 2026. The site has been inspected 4 times since May 2024. The Land Department took 21 site photos at its inspections.
Is Azizi Venice 14 delayed?
Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
Who is building Azizi Venice 14?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 14?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.