Azizi Venice 14 construction progress
Azizi Venice 14 in Dubai World Central was registered to complete in May 2026 and is still under construction. At the last site inspection, in June 2026, it was 30% built. The developer is Azizi Developments.
30%
Built, at the site inspection of 22 June 2026
6 months past its registered completion date
- Registered completion date
- May 2026
- Finish at recent pace
- January 2029
- Construction started
- May 2024
- First registered
- July 2024
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 3,438
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- عزيزى فينيس 14
- Project number
- 3073
- Site inspections
- 4
Schedule
Azizi Venice 14 was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around January 2029.
Site inspections
22 June 2026
30%+16 pts
14 November 2025
14%+4.9 pts
20 June 2025
8.9%+8.9 pts
6 May 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Venice 14?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Venice 14 handover date?
- The registered completion date was May 2026, and the register still lists Azizi Venice 14 as under construction. At the pace of its recent inspections the site would reach 100% around January 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Venice 14?
- Azizi Venice 14 was 30% built at the site inspection on 22 June 2026. The site has been inspected 4 times since May 2024. The Land Department took 21 site photos at its inspections.
- Is Azizi Venice 14 delayed?
- Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
- Who is building Azizi Venice 14?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 14?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.