Azizi Venice 12 construction progress

The registered completion date for Azizi Venice 12 in Dubai World Central is September 2027. At the last site inspection, in October 2026, it was 22% built. The developer is Azizi Developments.

22%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
September 2032
Construction started
September 2024
First registered
October 2024
Units
1,428
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزي فينيس 12
Project number
3318
Site inspections
4

Schedule

Between December 2025 and October 2026 the site added about 1.1 points a month. At that rate it would finish around September 2032, more than three months after its registered date of September 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

22%+6.3 pts

  • Azizi Venice 12 construction site, inspection photo 1, 15 October 2026
  • Azizi Venice 12 construction site, inspection photo 2, 15 October 2026
  • Azizi Venice 12 construction site, inspection photo 3, 15 October 2026
  • Azizi Venice 12 construction site, inspection photo 4, 15 October 2026

22 April 2026

15%+4.8 pts

  • Azizi Venice 12 construction site, inspection photo 1, 22 April 2026
  • Azizi Venice 12 construction site, inspection photo 2, 22 April 2026
  • Azizi Venice 12 construction site, inspection photo 3, 22 April 2026
  • Azizi Venice 12 construction site, inspection photo 4, 22 April 2026

9 December 2025

10%+10 pts

  • Azizi Venice 12 construction site, inspection photo 1, 9 December 2025
  • Azizi Venice 12 construction site, inspection photo 2, 9 December 2025
  • Azizi Venice 12 construction site, inspection photo 3, 9 December 2025
  • Azizi Venice 12 construction site, inspection photo 4, 9 December 2025

26 September 2024

0%

  • Azizi Venice 12 construction site, inspection photo 1, 26 September 2024
  • Azizi Venice 12 construction site, inspection photo 2, 26 September 2024

All 20 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 12?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 12 handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 12?
Azizi Venice 12 was 22% built at the site inspection on 15 October 2026. The site has been inspected 4 times since September 2024. The Land Department took 20 site photos at its inspections.
Is Azizi Venice 12 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Azizi Venice 12?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 12?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.