Azizi Venice 12 construction progress

Azizi Venice 12 in Dubai World Central is 15% built at the Land Department inspection of April 2026. Developer Azizi Developments. Completion registered for September 2027.

15%

Built, at the Land Department site inspection of 22 April 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
September 2032
Construction started
September 2024
Registered with the Land Department
October 2024
Units
1,428
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزي فينيس 12
Land Department project number
3318
Land Department site inspections
3

Schedule

Between December 2025 and April 2026 the site added about 1.1 points a month. At that rate it would finish around September 2032, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 April 2026

15%+4.8 pts

  • Azizi Venice 12 construction site, Land Department inspection photo 1, 22 April 2026
  • Azizi Venice 12 construction site, Land Department inspection photo 2, 22 April 2026
  • Azizi Venice 12 construction site, Land Department inspection photo 3, 22 April 2026
  • Azizi Venice 12 construction site, Land Department inspection photo 4, 22 April 2026

9 December 2025

10%+10 pts

  • Azizi Venice 12 construction site, Land Department inspection photo 1, 9 December 2025
  • Azizi Venice 12 construction site, Land Department inspection photo 2, 9 December 2025
  • Azizi Venice 12 construction site, Land Department inspection photo 3, 9 December 2025
  • Azizi Venice 12 construction site, Land Department inspection photo 4, 9 December 2025

26 September 2024

0%

  • Azizi Venice 12 construction site, Land Department inspection photo 1, 26 September 2024
  • Azizi Venice 12 construction site, Land Department inspection photo 2, 26 September 2024

All 12 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Venice 12?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Venice 12 be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around September 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Venice 12 is built?
15%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 3 times since September 2024.
Is Azizi Venice 12 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Azizi Venice 12?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 12?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.