Checking on an off-plan project, before the developer tells you.

Where the completion percentage comes from, how far to trust the handover date, and what escrow lets you do when a payment request arrives before the building has caught up. Written for someone who has already bought.

Updated

Every off-plan project in Dubai has a completion percentage on the Land Department's register, set by its technical audit at the latest site inspection. You can look it up by project name, number or plot on the Department's project tracking service. Check the date of that inspection too. On 8 November 2026, more than half the projects on the register had not been inspected in the previous three months.

In short

  • The percentage comes from the Land Department's own technical audit, so it is independent of the developer's marketing updates.

  • The registered completion date is a target, and RERA asks developers to update it as projects move. 256 of the 1,394 projects with a date had passed it on 8 November 2026.

  • A stage-linked instalment does not have to be paid until the project consultant confirms the stage has been reached.

  • Your payments belong in the project's escrow account. If the project is cancelled, that account is what buyers are repaid from.

Where the number comes from

The Land Department tracks every project under construction through a register usually called Mashrooi. The completion percentage on it is the result of the latest approved technical audit, an inspection of the site. The developer does not set it, which is the reason to read it alongside whatever progress update the developer sends.

You can search the project tracking service by project name, by project number or by plot number, and the result gives the percentage and the project's status. Mulki's off-plan trackerreads the same register every day and adds the inspection date and the Department's site photos to each project page.

If you want the full report on one unit

A buyer can ask for a report on a project's completion from RERA's technical auditor. The Land Department lists the fee as AED 15,000 per unit or villa, which makes it a tool for a serious dispute rather than for checking in on progress.

How fresh it is

A percentage means little without its date. We counted the inspections on the register on 8 November 2026: of the 1,558 projects with one recorded, 723 had been inspected in the previous three months. The rest were showing a figure older than that.

How recently Dubai's off-plan projects were inspected
Latest inspectionProjects
Within the last three months723
More than three months ago835
All with a recorded inspection1,558

Dubai Land Department Mashrooi register, read 8 November 2026. Active projects with a recorded inspection date.

An old inspection is not bad news in itself. It does mean the site may have moved since, in either direction, and it is worth looking at the photos before drawing conclusions from the number.

The handover date

The completion date on the register is the one the developer registered, and it can change. RERA reviews project status from time to time and asks developers to update their completion dates. So the register gives you the current target and nothing firmer.

Set against the percentage, though, it tells you a lot. A tower at 25% with a completion date four months away is unlikely to make it. On 8 November, 279 of the 372 projects due within twelve months were less than half built, and 256 had already passed their date. The November construction report breaks those down by community and developer.

When a payment request arrives

The Land Department describes off-plan payment schedules as based on completion rates: so much at one stage, so much at the next, the balance at handover. Its position is that the buyer can ask for a letter from the project's approved consultant confirming the stage has been reached, and is not obliged to pay until it is.

In practice that means checking the register before you pay. If the request says 50% and the latest inspection says 31%, ask for the consultant's letter. Plans that run on calendar dates rather than stages are a different contract, so it matters which one you signed.

What escrow does for you

Under Law No. 8 of 2007, a developer selling off-plan in Dubai has to open an escrow account for the project, in the project's name, with a bank RERA has approved as trustee. Every payment from buyers goes into it, including what was paid before the account was opened.

  • Money leaves against milestones.

    The developer reports a milestone, the trustee's engineer inspects the site, and only then is money released to the people building it.

  • It can only pay for the project.

    Contractors and consultants are paid from it, and marketing is capped at 5% of sales. It cannot be used for the developer's other costs.

  • 5% stays behind after completion.

    That share of what was paid in is held for a year after the project completes, to cover defects that appear in that time.

  • The developer's creditors cannot take it.

    The account belongs to the project. That matters most when a developer gets into trouble.

Escrow rules as set out in the Dubai Land Department's published answers on real estate escrow accounts, read 8 November 2026. Pay only into the escrow account named in your sale agreement.

When a project stalls

RERA watches progress. Where work has stopped or barely moved, it first gives the developer time to put it right. If nothing changes and there is no valid reason for the stoppage, a project with completion still at 5% or below can go into cancellation.

Cancellation hands the project to the Land Department's liquidation section, which moves the escrow balance into a trust account and pays buyers back, fully or in proportion to what is there. The developer is asked to refund buyers within 60 days, with extensions possible. One thing the Department cannot do is end your contract with the developer on your behalf. For a project that has not started, it will mediate, and beyond that the route is the courts.

If the developer will not register your sale

An off-plan sale should be registered with the Land Department. Where a developer refuses or delays, the buyer can apply to the Department's Real Estate Registration Assurance section with the sale documents to have the contract registered.

General information drawn from the Dubai Land Department's published answers on off-plan projects and escrow, and its project register, read 8 November 2026. Not legal advice. The terms of your own sale agreement decide much of what applies to you.

Questions

How do I check the handover date of an off-plan project in Dubai?

Look the project up on the Land Department's project tracking service, on its website or app, by project name, project number or plot number. It shows the completion percentage and the project's status. Mulki's off-plan tracker reads the same register and adds the registered completion date, the date of the latest inspection and the site photos. That date is the developer's target and RERA asks developers to update it, so read it next to the percentage.

What does the completion percentage on the register mean?

It is the share of the project the Land Department's technical audit found built at the latest inspection. It is a snapshot. On 8 November 2026, 835 of the 1,558 projects with a recorded inspection had not been inspected in the previous three months, so check the inspection date before trusting the number.

Do I have to pay an instalment if construction is behind schedule?

The Land Department describes off-plan payment schedules as based on completion rates. According to the Department, when a payment request arrives you can ask for a letter from the project's approved consultant confirming the stage has been reached, and you are not obliged to pay until it is confirmed. A plan tied to calendar dates instead works differently, so read your sale agreement first.

How do I know my money is protected?

Every payment for an off-plan unit has to go into the project's escrow account, held in the project's name by a bank RERA has approved. The developer cannot spend it freely: it pays contractors and consultants against inspected milestones, and the developer's creditors cannot claim it. Pay into the escrow account named in your agreement and nowhere else.

What happens to my money if an off-plan project is cancelled?

Once a project is cancelled, the Land Department's liquidation section moves the escrow balance into a trust account and pays buyers back, in full or in proportion to what is there. The developer is asked to refund buyers within 60 days, which can be extended. The Department says there is no fixed timeline for liquidation itself.

Can the developer change the completion date?

It can change. RERA reviews project status from time to time and asks developers to update their completion dates and completion rates. A project that looks late on the register may be working to a new date the register has not shown yet, and one that looks on time may already have had its date moved.
An unfinished floor of a Downtown Dubai tower, bare concrete and loose cabling, with Burj Khalifa beyond the edge

Own an off-plan unit? Mulki follows every inspection until the keys arrive.