Azizi Venice 15 construction progress
The registered completion date for Azizi Venice 15 in Dubai World Central is May 2027. At the last site inspection, in November 2026, it was 3.3% built. The developer is Azizi Developments.
3.3%
Built, at the site inspection of 24 November 2026
Running behind its date
- Registered completion date
- May 2027
- Finish at recent pace
- July 2072
- Construction started
- May 2025
- First registered
- June 2025
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 1,855
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- عزيزي فينيس 15
- Project number
- 3741
- Site inspections
- 2
Schedule
Between May 2025 and November 2026 the site added about 0.2 points a month. At that rate it would finish around July 2072, more than three months after its registered date of May 2027.
Site inspections
24 November 2026
3.3%+3.3 pts
6 May 2025
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Venice 15?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Venice 15 handover date?
- The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2072. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Venice 15?
- Azizi Venice 15 was 3.3% built at the site inspection on 24 November 2026. The site has been inspected 2 times since May 2025. The Land Department took 5 site photos at its inspections.
- Is Azizi Venice 15 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Azizi Venice 15?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 15?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


