Golf Dale construction progress

Golf Dale in Dubai World Central is 0.3% built at the Land Department inspection of April 2026. Developer Emaar Dubai South Dwc. Completion registered for December 2028.

0.3%

Built, at the Land Department site inspection of 30 April 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
March 2551
Construction started
May 2025
Registered with the Land Department
December 2024
Units
200
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جولف دايل
Land Department project number
3427
Land Department site inspections
2

Schedule

Between November 2024 and April 2026 the site added about 0.0 points a month. At that rate it would finish around March 2551, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 April 2026

0.3%+0.3 pts

  • Golf Dale construction site, Land Department inspection photo 1, 30 April 2026
  • Golf Dale construction site, Land Department inspection photo 2, 30 April 2026
  • Golf Dale construction site, Land Department inspection photo 3, 30 April 2026

27 November 2024

0%

  • Golf Dale construction site, Land Department inspection photo 1, 27 November 2024
  • Golf Dale construction site, Land Department inspection photo 2, 27 November 2024

All 5 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average. Golf Dale is behind that average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Dale?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Golf Dale be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around March 2551. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Golf Dale is built?
0.3%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since November 2024.
Is Golf Dale delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Golf Dale?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Dale?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.