Golf Dale construction progress
The registered completion date for Golf Dale in Dubai World Central is December 2028. At the last site inspection, in November 2026, it was 4.3% built. The developer is Emaar Dubai South Dwc.
4.3%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- July 2039
- Construction started
- May 2025
- First registered
- December 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 200
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- جولف دايل
- Project number
- 3427
- Site inspections
- 3
Schedule
Between April 2026 and November 2026 the site added about 0.6 points a month. At that rate it would finish around July 2039, more than three months after its registered date of December 2028.
Site inspections
9 November 2026
4.3%+4.0 pts
30 April 2026
0.3%+0.3 pts
27 November 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Golf Dale?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Golf Dale handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Golf Dale?
- Golf Dale was 4.3% built at the site inspection on 9 November 2026. The site has been inspected 3 times since November 2024. The Land Department took 8 site photos at its inspections.
- Is Golf Dale delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Golf Dale?
- The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Golf Dale?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 2Also by Emaar Dubai South Dwc. 92%, Due December 2026.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 57%.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpg&w=3840&q=75)