Fairway Villas 2 construction progress

The registered completion date for Fairway Villas 2 in Dubai World Central is December 2026. At the last site inspection, in August 2026, it was 92% built. The developer is Emaar Dubai South Dwc.

92%

Built, at the site inspection of 17 August 2026

On pace for its date

Registered completion date
December 2026
Finish at recent pace
October 2026
Construction started
July 2023
First registered
May 2023
Units
176
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيرواي فيلاز 2
Project number
2604
Site inspections
11

Schedule

Since November 2025 Fairway Villas 2 has added about 3.7 points a month. That puts 100% around October 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

92%+9.3 pts

  • Fairway Villas 2 construction site, inspection photo 1, 17 August 2026
  • Fairway Villas 2 construction site, inspection photo 2, 17 August 2026
  • Fairway Villas 2 construction site, inspection photo 3, 17 August 2026
  • Fairway Villas 2 construction site, inspection photo 4, 17 August 2026

7 July 2026

83%+15 pts

  • Fairway Villas 2 construction site, inspection photo 1, 7 July 2026
  • Fairway Villas 2 construction site, inspection photo 2, 7 July 2026
  • Fairway Villas 2 construction site, inspection photo 3, 7 July 2026
  • Fairway Villas 2 construction site, inspection photo 4, 7 July 2026

12 March 2026

68%+8.0 pts

  • Fairway Villas 2 construction site, inspection photo 1, 12 March 2026
  • Fairway Villas 2 construction site, inspection photo 2, 12 March 2026
  • Fairway Villas 2 construction site, inspection photo 3, 12 March 2026
  • Fairway Villas 2 construction site, inspection photo 4, 12 March 2026

20 November 2025

60%+14 pts

  • Fairway Villas 2 construction site, inspection photo 1, 20 November 2025
  • Fairway Villas 2 construction site, inspection photo 2, 20 November 2025
  • Fairway Villas 2 construction site, inspection photo 3, 20 November 2025
  • Fairway Villas 2 construction site, inspection photo 4, 20 November 2025

18 July 2025

46%+9.3 pts

  • Fairway Villas 2 construction site, inspection photo 1, 18 July 2025
  • Fairway Villas 2 construction site, inspection photo 2, 18 July 2025
  • Fairway Villas 2 construction site, inspection photo 3, 18 July 2025
  • Fairway Villas 2 construction site, inspection photo 4, 18 July 2025

25 April 2025

37%+19 pts

  • Fairway Villas 2 construction site, inspection photo 1, 25 April 2025
  • Fairway Villas 2 construction site, inspection photo 2, 25 April 2025
  • Fairway Villas 2 construction site, inspection photo 3, 25 April 2025
  • Fairway Villas 2 construction site, inspection photo 4, 25 April 2025

8 January 2025

18%+12 pts

  • Fairway Villas 2 construction site, inspection photo 1, 8 January 2025
  • Fairway Villas 2 construction site, inspection photo 2, 8 January 2025
  • Fairway Villas 2 construction site, inspection photo 3, 8 January 2025
  • Fairway Villas 2 construction site, inspection photo 4, 8 January 2025

30 September 2024

5.3%+4.6 pts

  • Fairway Villas 2 construction site, inspection photo 1, 30 September 2024
  • Fairway Villas 2 construction site, inspection photo 2, 30 September 2024
  • Fairway Villas 2 construction site, inspection photo 3, 30 September 2024
  • Fairway Villas 2 construction site, inspection photo 4, 30 September 2024

25 March 2024

0.6%+0.2 pts

  • Fairway Villas 2 construction site, inspection photo 1, 25 March 2024
  • Fairway Villas 2 construction site, inspection photo 2, 25 March 2024
  • Fairway Villas 2 construction site, inspection photo 3, 25 March 2024
  • Fairway Villas 2 construction site, inspection photo 4, 25 March 2024

28 September 2023

0.4%+0.4 pts

  • Fairway Villas 2 construction site, inspection photo 1, 28 September 2023
  • Fairway Villas 2 construction site, inspection photo 2, 28 September 2023
  • Fairway Villas 2 construction site, inspection photo 3, 28 September 2023
  • Fairway Villas 2 construction site, inspection photo 4, 28 September 2023

All 65 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Fairway Villas 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Fairway Villas 2 handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Fairway Villas 2?
Fairway Villas 2 was 92% built at the site inspection on 17 August 2026. The site has been inspected 11 times since March 2023. The Land Department took 65 site photos at its inspections.
Is Fairway Villas 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Fairway Villas 2?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Fairway Villas 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.