Azizi Venice 16 construction progress

The registered completion date for Azizi Venice 16 in Dubai World Central is June 2027. At the last site inspection, in November 2026, it was 3.7% built. The developer is Azizi Developments.

3.7%

Built, at the site inspection of 16 November 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
January 2065
Construction started
June 2025
First registered
June 2025
Units
1,055
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي فينيس 16
Project number
3814
Site inspections
2

Schedule

Between June 2025 and November 2026 the site added about 0.2 points a month. At that rate it would finish around January 2065, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

3.7%+3.7 pts

  • Azizi Venice 16 construction site, inspection photo 1, 16 November 2026
  • Azizi Venice 16 construction site, inspection photo 2, 16 November 2026

3 June 2025

0%

  • Azizi Venice 16 construction site, inspection photo 1, 3 June 2025
  • Azizi Venice 16 construction site, inspection photo 2, 3 June 2025

All 4 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 16?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 16 handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2065. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 16?
Azizi Venice 16 was 3.7% built at the site inspection on 16 November 2026. The site has been inspected 2 times since June 2025. The Land Department took 4 site photos at its inspections.
Is Azizi Venice 16 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Azizi Venice 16?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 16?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.