Azizi Venice 9 construction progress

No completion date is registered for Azizi Venice 9 in Dubai World Central yet. At the last site inspection, in June 2026, it was 54% built. The developer is Azizi Developments.

54%

Built, at the site inspection of 29 June 2026

Finish at recent pace
December 2028
Construction started
October 2023
First registered
November 2023
Units
778
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزى فينيس 9
Project number
2829
Site inspections
4

Schedule

Since August 2025 Azizi Venice 9 has added about 1.5 points a month. At that rate the site reaches 100% around December 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

29 June 2026

54%+6.5 pts

  • Azizi Venice 9 construction site, inspection photo 1, 29 June 2026
  • Azizi Venice 9 construction site, inspection photo 2, 29 June 2026
  • Azizi Venice 9 construction site, inspection photo 3, 29 June 2026

6 January 2026

47%+10.0 pts

  • Azizi Venice 9 construction site, inspection photo 1, 6 January 2026
  • Azizi Venice 9 construction site, inspection photo 2, 6 January 2026
  • Azizi Venice 9 construction site, inspection photo 3, 6 January 2026
  • Azizi Venice 9 construction site, inspection photo 4, 6 January 2026

7 August 2025

38%+38 pts

  • Azizi Venice 9 construction site, inspection photo 1, 7 August 2025
  • Azizi Venice 9 construction site, inspection photo 2, 7 August 2025
  • Azizi Venice 9 construction site, inspection photo 3, 7 August 2025
  • Azizi Venice 9 construction site, inspection photo 4, 7 August 2025

25 October 2023

0%

  • Azizi Venice 9 construction site, inspection photo 1, 25 October 2023
  • Azizi Venice 9 construction site, inspection photo 2, 25 October 2023

All 23 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 9?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 9 handover date?
No completion date is on record for Azizi Venice 9 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Azizi Venice 9?
Azizi Venice 9 was 54% built at the site inspection on 29 June 2026. The site has been inspected 4 times since October 2023. The Land Department took 23 site photos at its inspections.
Who is building Azizi Venice 9?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 9?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.