Expo City Sky Residences construction progress
No completion date is registered for Expo City Sky Residences in Dubai World Central yet. At the last site inspection, in August 2026, it was 53% built. The developer is Expo City Sky Residences Development Fzco.
53%
Built, at the site inspection of 18 August 2026
- Finish at recent pace
- November 2027
- Construction started
- June 2024
- First registered
- January 2024
- Developer
- Expo City Sky Residences Development Fzco
- Community
- Dubai World Central
- Units
- 437
- Escrow bank
- Emirates NBD
- Name in Arabic
- إكسبو سيتي سكاي ريزيدنسز
- Project number
- 2617
- Site inspections
- 6
Schedule
Since December 2025 Expo City Sky Residences has added about 3.2 points a month. At that rate the site reaches 100% around November 2027. No completion date is on record to compare it with.
Site inspections
18 August 2026
53%+14 pts
14 April 2026
39%+10 pts
26 December 2025
28%+11 pts
4 July 2025
18%+14 pts
14 October 2024
3.6%+3.6 pts
30 March 2023
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Own a unit in Expo City Sky Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Expo City Sky Residences handover date?
- No completion date is on record for Expo City Sky Residences yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Expo City Sky Residences?
- Expo City Sky Residences was 53% built at the site inspection on 18 August 2026. The site has been inspected 6 times since March 2023. The Land Department took 43 site photos at its inspections.
- Who is building Expo City Sky Residences?
- The registered developer is Expo City Sky Residences Development Fzco.
- Which bank holds the escrow account for Expo City Sky Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)