Expo City Sky Residences construction progress
Expo City Sky Residences in Dubai World Central is 53% built at the Land Department inspection of August 2026. Developer Expo City Sky Residences Development Fzco.
53%
Built, at the Land Department site inspection of 18 August 2026
- Finish at recent pace
- November 2027
- Construction started
- June 2024
- Registered with the Land Department
- January 2024
- Developer
- Expo City Sky Residences Development Fzco
- Community
- Dubai World Central
- Units
- 437
- Escrow bank
- Emirates NBD
- Name in Arabic
- إكسبو سيتي سكاي ريزيدنسز
- Land Department project number
- 2617
- Land Department site inspections
- 6
Schedule
Since December 2025 Expo City Sky Residences has added about 3.2 points a month. At that rate the site reaches 100% around November 2027. The Land Department has no completion date on record to compare it with.
Site inspections
18 August 2026
53%+14 pts
14 April 2026
39%+10 pts
26 December 2025
28%+11 pts
4 July 2025
18%+14 pts
14 October 2024
3.6%+3.6 pts
30 March 2023
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Own a unit in Expo City Sky Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Expo City Sky Residences be completed?
- The Land Department has no completion date on record for Expo City Sky Residences yet.
- How much of Expo City Sky Residences is built?
- 53%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 6 times since March 2023.
- Who is building Expo City Sky Residences?
- The registered developer is Expo City Sky Residences Development Fzco.
- Which bank holds the escrow account for Expo City Sky Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Azizi Venice 4Nearby in Dubai World Central. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)