Skip to content

Greenville construction progress

Greenville in Dubai World Central is 46% built at the Land Department inspection of May 2026. Developer Emaar Dubai South Dwc. Completion registered for March 2029.

46%

Built, at the Land Department site inspection of 14 May 2026

On pace for its date

Completion date (Land Department)
March 2029
Finish at recent pace
March 2027
Construction started
January 2025
Registered with the Land Department
October 2024
Units
140
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جرينفل
Land Department project number
3316
Land Department site inspections
5

Schedule

Since October 2025 Greenville has added about 5.3 points a month. That puts 100% around March 2027, within three months of its registered completion date of March 2029.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 May 2026

46%+16 pts

  • Greenville construction site, Land Department inspection photo 1, 14 May 2026
  • Greenville construction site, Land Department inspection photo 2, 14 May 2026
  • Greenville construction site, Land Department inspection photo 3, 14 May 2026
  • Greenville construction site, Land Department inspection photo 4, 14 May 2026

26 January 2026

30%+22 pts

  • Greenville construction site, Land Department inspection photo 1, 26 January 2026
  • Greenville construction site, Land Department inspection photo 2, 26 January 2026
  • Greenville construction site, Land Department inspection photo 3, 26 January 2026
  • Greenville construction site, Land Department inspection photo 4, 26 January 2026

8 October 2025

7.9%+6.9 pts

  • Greenville construction site, Land Department inspection photo 1, 8 October 2025
  • Greenville construction site, Land Department inspection photo 2, 8 October 2025
  • Greenville construction site, Land Department inspection photo 3, 8 October 2025
  • Greenville construction site, Land Department inspection photo 4, 8 October 2025

12 May 2025

0.9%+0.9 pts

  • Greenville construction site, Land Department inspection photo 1, 12 May 2025
  • Greenville construction site, Land Department inspection photo 2, 12 May 2025
  • Greenville construction site, Land Department inspection photo 3, 12 May 2025

27 September 2024

0%

  • Greenville construction site, Land Department inspection photo 1, 27 September 2024
  • Greenville construction site, Land Department inspection photo 2, 27 September 2024
  • Greenville construction site, Land Department inspection photo 3, 27 September 2024

All 27 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenville?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Greenville be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Greenville is built?
46%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 5 times since September 2024.
Is Greenville delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
Who is building Greenville?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Greenville?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.