Greenville construction progress

The registered completion date for Greenville in Dubai World Central is March 2029. At the last site inspection, in May 2026, it was 46% built. The developer is Emaar Dubai South Dwc.

46%

Built, at the site inspection of 14 May 2026

On pace for its date

Registered completion date
March 2029
Finish at recent pace
March 2027
Construction started
January 2025
First registered
October 2024
Units
140
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جرينفل
Project number
3316
Site inspections
5

Schedule

Since October 2025 Greenville has added about 5.3 points a month. That puts 100% around March 2027, within three months of its registered completion date of March 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

46%+16 pts

  • Greenville construction site, inspection photo 1, 14 May 2026
  • Greenville construction site, inspection photo 2, 14 May 2026
  • Greenville construction site, inspection photo 3, 14 May 2026
  • Greenville construction site, inspection photo 4, 14 May 2026

26 January 2026

30%+22 pts

  • Greenville construction site, inspection photo 1, 26 January 2026
  • Greenville construction site, inspection photo 2, 26 January 2026
  • Greenville construction site, inspection photo 3, 26 January 2026
  • Greenville construction site, inspection photo 4, 26 January 2026

8 October 2025

7.9%+6.9 pts

  • Greenville construction site, inspection photo 1, 8 October 2025
  • Greenville construction site, inspection photo 2, 8 October 2025
  • Greenville construction site, inspection photo 3, 8 October 2025
  • Greenville construction site, inspection photo 4, 8 October 2025

12 May 2025

0.9%+0.9 pts

  • Greenville construction site, inspection photo 1, 12 May 2025
  • Greenville construction site, inspection photo 2, 12 May 2025
  • Greenville construction site, inspection photo 3, 12 May 2025

27 September 2024

0%

  • Greenville construction site, inspection photo 1, 27 September 2024
  • Greenville construction site, inspection photo 2, 27 September 2024
  • Greenville construction site, inspection photo 3, 27 September 2024

All 27 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenville?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Greenville handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Greenville?
Greenville was 46% built at the site inspection on 14 May 2026. The site has been inspected 5 times since September 2024. The Land Department took 27 site photos at its inspections.
Is Greenville delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
Who is building Greenville?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Greenville?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.