Greenville construction progress
The registered completion date for Greenville in Dubai World Central is March 2029. At the last site inspection, in May 2026, it was 46% built. The developer is Emaar Dubai South Dwc.
46%
Built, at the site inspection of 14 May 2026
On pace for its date
- Registered completion date
- March 2029
- Finish at recent pace
- March 2027
- Construction started
- January 2025
- First registered
- October 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 140
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- جرينفل
- Project number
- 3316
- Site inspections
- 5
Schedule
Since October 2025 Greenville has added about 5.3 points a month. That puts 100% around March 2027, within three months of its registered completion date of March 2029.
Site inspections
14 May 2026
46%+16 pts
26 January 2026
30%+22 pts
8 October 2025
7.9%+6.9 pts
12 May 2025
0.9%+0.9 pts
27 September 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenville?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Greenville handover date?
- The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Greenville?
- Greenville was 46% built at the site inspection on 14 May 2026. The site has been inspected 5 times since September 2024. The Land Department took 27 site photos at its inspections.
- Is Greenville delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
- Who is building Greenville?
- The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenville?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 2Also by Emaar Dubai South Dwc. 92%, Due December 2026.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 57%.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)











.jpeg&w=3840&q=75)