Golf Meadow construction progress
Golf Meadow in Dubai World Central is 4.5% built at the Land Department inspection of July 2026. Developer Emaar Dubai South Dwc. Completion registered for July 2029.
4.5%
Built, at the Land Department site inspection of 19 July 2026
Running behind its date
- Completion date (Land Department)
- July 2029
- Finish at recent pace
- July 2037
- Construction started
- August 2025
- Registered with the Land Department
- March 2025
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 188
- Escrow bank
- Mashreq Bank
- Name in Arabic
- جولف ميدو
- Land Department project number
- 3579
- Land Department site inspections
- 3
Schedule
Between March 2026 and July 2026 the site added about 0.7 points a month. At that rate it would finish around July 2037, more than three months after the July 2029 date registered with the Land Department.
Site inspections
19 July 2026
4.5%+2.8 pts
24 March 2026
1.8%+1.8 pts
25 February 2025
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Golf Meadow?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Golf Meadow be completed?
- The completion date registered with the Dubai Land Department is July 2029. At the pace of its recent inspections the site would reach 100% around July 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Golf Meadow is built?
- 4.5%, measured at the Land Department site inspection on 19 July 2026. The Land Department engineers have inspected the site 3 times since February 2025.
- Is Golf Meadow delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
- Who is building Golf Meadow?
- The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Golf Meadow?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 30%.
- Greenway 2Also by Emaar Dubai South Dwc. 34%, Due May 2028.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.