Golf Meadow construction progress

The registered completion date for Golf Meadow in Dubai World Central is July 2029. At the last site inspection, in July 2026, it was 4.5% built. The developer is Emaar Dubai South Dwc.

4.5%

Built, at the site inspection of 19 July 2026

Running behind its date

Registered completion date
July 2029
Finish at recent pace
July 2037
Construction started
August 2025
First registered
March 2025
Units
188
Escrow bank
Mashreq Bank
Name in Arabic
جولف ميدو
Project number
3579
Site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 0.7 points a month. At that rate it would finish around July 2037, more than three months after its registered date of July 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 July 2026

4.5%+2.8 pts

  • Golf Meadow construction site, inspection photo 1, 19 July 2026
  • Golf Meadow construction site, inspection photo 2, 19 July 2026

24 March 2026

1.8%+1.8 pts

  • Golf Meadow construction site, inspection photo 1, 24 March 2026
  • Golf Meadow construction site, inspection photo 2, 24 March 2026
  • Golf Meadow construction site, inspection photo 3, 24 March 2026
  • Golf Meadow construction site, inspection photo 4, 24 March 2026

25 February 2025

0%

  • Golf Meadow construction site, inspection photo 1, 25 February 2025
  • Golf Meadow construction site, inspection photo 2, 25 February 2025

All 8 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Meadow?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Meadow handover date?
The registered completion date is July 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Meadow?
Golf Meadow was 4.5% built at the site inspection on 19 July 2026. The site has been inspected 3 times since February 2025. The Land Department took 8 site photos at its inspections.
Is Golf Meadow delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2029.
Who is building Golf Meadow?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Meadow?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.