Azizi Venice 5 construction progress

Azizi Venice 5 in Dubai World Central was registered to complete in October 2025 and is still under construction. At the last site inspection, in May 2026, it was 63% built. The developer is Azizi Developments.

63%

Built, at the site inspection of 13 May 2026

13 months past its registered completion date

Registered completion date
October 2025
Finish at recent pace
December 2027
Construction started
October 2023
First registered
November 2023
Units
484
Escrow bank
Bank of Sharjah
Name in Arabic
عزيزى فينيس 5
Project number
2822
Site inspections
6

Schedule

Azizi Venice 5 was registered to complete in October 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 May 2026

63%+7.6 pts

  • Azizi Venice 5 construction site, inspection photo 1, 13 May 2026
  • Azizi Venice 5 construction site, inspection photo 2, 13 May 2026
  • Azizi Venice 5 construction site, inspection photo 3, 13 May 2026
  • Azizi Venice 5 construction site, inspection photo 4, 13 May 2026

21 January 2026

56%+11 pts

  • Azizi Venice 5 construction site, inspection photo 1, 21 January 2026
  • Azizi Venice 5 construction site, inspection photo 2, 21 January 2026
  • Azizi Venice 5 construction site, inspection photo 3, 21 January 2026
  • Azizi Venice 5 construction site, inspection photo 4, 21 January 2026

31 July 2025

45%+11 pts

  • Azizi Venice 5 construction site, inspection photo 1, 31 July 2025
  • Azizi Venice 5 construction site, inspection photo 2, 31 July 2025
  • Azizi Venice 5 construction site, inspection photo 3, 31 July 2025
  • Azizi Venice 5 construction site, inspection photo 4, 31 July 2025

10 April 2025

35%+19 pts

  • Azizi Venice 5 construction site, inspection photo 1, 10 April 2025
  • Azizi Venice 5 construction site, inspection photo 2, 10 April 2025
  • Azizi Venice 5 construction site, inspection photo 3, 10 April 2025
  • Azizi Venice 5 construction site, inspection photo 4, 10 April 2025

3 October 2024

16%+16 pts

  • Azizi Venice 5 construction site, inspection photo 1, 3 October 2024
  • Azizi Venice 5 construction site, inspection photo 2, 3 October 2024
  • Azizi Venice 5 construction site, inspection photo 3, 3 October 2024
  • Azizi Venice 5 construction site, inspection photo 4, 3 October 2024

25 October 2023

0%

  • Azizi Venice 5 construction site, inspection photo 1, 25 October 2023
  • Azizi Venice 5 construction site, inspection photo 2, 25 October 2023
  • Azizi Venice 5 construction site, inspection photo 3, 25 October 2023

All 40 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 5?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 5 handover date?
The registered completion date was October 2025, and the register still lists Azizi Venice 5 as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 5?
Azizi Venice 5 was 63% built at the site inspection on 13 May 2026. The site has been inspected 6 times since October 2023. The Land Department took 40 site photos at its inspections.
Is Azizi Venice 5 delayed?
Yes. Its registered completion date of October 2025 has passed and the project is still listed as under construction.
Who is building Azizi Venice 5?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 5?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.