Azizi Venice 8 construction progress

Azizi Venice 8 in Dubai World Central is 53% built at the Land Department inspection of July 2026. Developer Azizi Developments.

53%

Built, at the Land Department site inspection of 7 July 2026

Finish at recent pace
June 2029
Construction started
October 2023
Registered with the Land Department
November 2023
Units
778
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزى فينيس 8
Land Department project number
2830
Land Department site inspections
4

Schedule

Since August 2025 Azizi Venice 8 has added about 1.3 points a month. At that rate the site reaches 100% around June 2029. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

7 July 2026

53%+8.6 pts

  • Azizi Venice 8 construction site, Land Department inspection photo 1, 7 July 2026
  • Azizi Venice 8 construction site, Land Department inspection photo 2, 7 July 2026
  • Azizi Venice 8 construction site, Land Department inspection photo 3, 7 July 2026

16 December 2025

44%+6.1 pts

  • Azizi Venice 8 construction site, Land Department inspection photo 1, 16 December 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 2, 16 December 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 3, 16 December 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 4, 16 December 2025

7 August 2025

38%+38 pts

  • Azizi Venice 8 construction site, Land Department inspection photo 1, 7 August 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 2, 7 August 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 3, 7 August 2025
  • Azizi Venice 8 construction site, Land Department inspection photo 4, 7 August 2025

25 October 2023

0%

  • Azizi Venice 8 construction site, Land Department inspection photo 1, 25 October 2023
  • Azizi Venice 8 construction site, Land Department inspection photo 2, 25 October 2023

All 24 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Venice 8?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Venice 8 be completed?
The Land Department has no completion date on record for Azizi Venice 8 yet.
How much of Azizi Venice 8 is built?
53%, measured at the Land Department site inspection on 7 July 2026. The Land Department engineers have inspected the site 4 times since October 2023.
Who is building Azizi Venice 8?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 8?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.