Expo City Al Waha Residences 02 construction progress
Expo City Al Waha Residences 02 in Dubai World Central is 61% built at the Land Department inspection of August 2026. Developer Expo City Al Waha Residences Development Fzco. Completion registered for June 2027.
61%
Built, at the Land Department site inspection of 26 August 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- September 2028
- Construction started
- July 2025
- Registered with the Land Department
- February 2025
- Developer
- Expo City Al Waha Residences Development Fzco
- Community
- Dubai World Central
- Units
- 280
- Escrow bank
- Emirates NBD
- Name in Arabic
- إكسبو سيتي الواحة ريزيدنسز 02
- Land Department project number
- 3567
- Land Department site inspections
- 3
Schedule
Between April 2026 and August 2026 the site added about 1.6 points a month. At that rate it would finish around September 2028, more than three months after the June 2027 date registered with the Land Department.
Site inspections
26 August 2026
61%+6.5 pts
20 April 2026
55%+6.6 pts
19 May 2025
48%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Expo City Al Waha Residences Development Fzco has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Expo City Al Waha Residences 02?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Expo City Al Waha Residences 02 be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around September 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Expo City Al Waha Residences 02 is built?
- 61%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 3 times since May 2025.
- Is Expo City Al Waha Residences 02 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Expo City Al Waha Residences 02?
- The registered developer is Expo City Al Waha Residences Development Fzco. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Expo City Al Waha Residences 02?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Expo City Al Waha Residences 01Also by Expo City Al Waha Residences Development Fzco. 66%, Due June 2027.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



