Golf Point construction progress
Golf Point in Dubai World Central is 4.8% built at the Land Department inspection of June 2025. Developer Emaar Dubai South Dwc. Completion registered for October 2028.
4.8%
Built, at the Land Department site inspection of 30 June 2025
Running behind its date
- Completion date (Land Department)
- October 2028
- Finish at recent pace
- September 2043
- Construction started
- December 2024
- Registered with the Land Department
- August 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 590
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- جولف بوينت
- Land Department project number
- 3215
- Land Department site inspections
- 3
Schedule
Between July 2024 and June 2025 the site added about 0.4 points a month. At that rate it would finish around September 2043, more than three months after the October 2028 date registered with the Land Department.
Site inspections
30 June 2025
4.8%+4.4 pts
17 February 2025
0.3%+0.3 pts
31 July 2024
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Golf Point?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Golf Point be completed?
- The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around September 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Golf Point is built?
- 4.8%, measured at the Land Department site inspection on 30 June 2025. The Land Department engineers have inspected the site 3 times since July 2024.
- Is Golf Point delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Golf Point?
- The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Golf Point?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 30%.
- Greenway 2Also by Emaar Dubai South Dwc. 34%, Due May 2028.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.