Golf Point construction progress

The registered completion date for Golf Point in Dubai World Central is October 2028. At the last site inspection, in November 2026, it was 5.4% built. The developer is Emaar Dubai South Dwc.

5.4%

Built, at the site inspection of 4 November 2026

Running behind its date

Registered completion date
October 2028
Finish at recent pace
August 2246
Construction started
December 2024
First registered
August 2024
Units
590
Escrow bank
Dubai Islamic Bank
Name in Arabic
جولف بوينت
Project number
3215
Site inspections
4

Schedule

Between June 2025 and November 2026 the site added about 0.0 points a month. At that rate it would finish around August 2246, more than three months after its registered date of October 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

5.4%+0.6 pts

  • Golf Point construction site, inspection photo 1, 4 November 2026
  • Golf Point construction site, inspection photo 2, 4 November 2026
  • Golf Point construction site, inspection photo 3, 4 November 2026
  • Golf Point construction site, inspection photo 4, 4 November 2026

30 June 2025

4.8%+4.4 pts

  • Golf Point construction site, inspection photo 1, 30 June 2025
  • Golf Point construction site, inspection photo 2, 30 June 2025
  • Golf Point construction site, inspection photo 3, 30 June 2025
  • Golf Point construction site, inspection photo 4, 30 June 2025

17 February 2025

0.3%+0.3 pts

  • Golf Point construction site, inspection photo 1, 17 February 2025
  • Golf Point construction site, inspection photo 2, 17 February 2025
  • Golf Point construction site, inspection photo 3, 17 February 2025
  • Golf Point construction site, inspection photo 4, 17 February 2025

31 July 2024

0%

  • Golf Point construction site, inspection photo 1, 31 July 2024
  • Golf Point construction site, inspection photo 2, 31 July 2024

All 18 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Point?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Point handover date?
The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2246. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Point?
Golf Point was 5.4% built at the site inspection on 4 November 2026. The site has been inspected 4 times since July 2024. The Land Department took 18 site photos at its inspections.
Is Golf Point delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Golf Point?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Point?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.