Golf Point construction progress

Golf Point in Dubai World Central is 4.8% built at the Land Department inspection of June 2025. Developer Emaar Dubai South Dwc. Completion registered for October 2028.

4.8%

Built, at the Land Department site inspection of 30 June 2025

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
September 2043
Construction started
December 2024
Registered with the Land Department
August 2024
Units
590
Escrow bank
Dubai Islamic Bank
Name in Arabic
جولف بوينت
Land Department project number
3215
Land Department site inspections
3

Schedule

Between July 2024 and June 2025 the site added about 0.4 points a month. At that rate it would finish around September 2043, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2025

4.8%+4.4 pts

  • Golf Point construction site, Land Department inspection photo 1, 30 June 2025
  • Golf Point construction site, Land Department inspection photo 2, 30 June 2025
  • Golf Point construction site, Land Department inspection photo 3, 30 June 2025
  • Golf Point construction site, Land Department inspection photo 4, 30 June 2025

17 February 2025

0.3%+0.3 pts

  • Golf Point construction site, Land Department inspection photo 1, 17 February 2025
  • Golf Point construction site, Land Department inspection photo 2, 17 February 2025
  • Golf Point construction site, Land Department inspection photo 3, 17 February 2025
  • Golf Point construction site, Land Department inspection photo 4, 17 February 2025

31 July 2024

0%

  • Golf Point construction site, Land Department inspection photo 1, 31 July 2024
  • Golf Point construction site, Land Department inspection photo 2, 31 July 2024

All 11 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Point?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Golf Point be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around September 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Golf Point is built?
4.8%, measured at the Land Department site inspection on 30 June 2025. The Land Department engineers have inspected the site 3 times since July 2024.
Is Golf Point delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Golf Point?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Point?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.