Greenway 2 construction progress

The registered completion date for Greenway 2 in Dubai World Central is May 2028. At the last site inspection, in July 2026, it was 34% built. The developer is Emaar Dubai South Dwc.

34%

Built, at the site inspection of 29 July 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
December 2028
Construction started
October 2024
First registered
June 2024
Units
492
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
غرين واي 2
Project number
3121
Site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 2.3 points a month. At that rate it would finish around December 2028, more than three months after its registered date of May 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 July 2026

34%+10 pts

  • Greenway 2 construction site, inspection photo 1, 29 July 2026
  • Greenway 2 construction site, inspection photo 2, 29 July 2026
  • Greenway 2 construction site, inspection photo 3, 29 July 2026
  • Greenway 2 construction site, inspection photo 4, 29 July 2026

21 April 2026

24%+11 pts

  • Greenway 2 construction site, inspection photo 1, 21 April 2026
  • Greenway 2 construction site, inspection photo 2, 21 April 2026
  • Greenway 2 construction site, inspection photo 3, 21 April 2026
  • Greenway 2 construction site, inspection photo 4, 21 April 2026

16 October 2025

13%+8.6 pts

  • Greenway 2 construction site, inspection photo 1, 16 October 2025
  • Greenway 2 construction site, inspection photo 2, 16 October 2025
  • Greenway 2 construction site, inspection photo 3, 16 October 2025
  • Greenway 2 construction site, inspection photo 4, 16 October 2025

12 June 2025

4.4%+2.9 pts

  • Greenway 2 construction site, inspection photo 1, 12 June 2025
  • Greenway 2 construction site, inspection photo 2, 12 June 2025
  • Greenway 2 construction site, inspection photo 3, 12 June 2025
  • Greenway 2 construction site, inspection photo 4, 12 June 2025

16 December 2024

1.5%+1.5 pts

  • Greenway 2 construction site, inspection photo 1, 16 December 2024
  • Greenway 2 construction site, inspection photo 2, 16 December 2024
  • Greenway 2 construction site, inspection photo 3, 16 December 2024

30 May 2024

0%

  • Greenway 2 construction site, inspection photo 1, 30 May 2024
  • Greenway 2 construction site, inspection photo 2, 30 May 2024
  • Greenway 2 construction site, inspection photo 3, 30 May 2024

All 35 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenway 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Greenway 2 handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Greenway 2?
Greenway 2 was 34% built at the site inspection on 29 July 2026. The site has been inspected 6 times since May 2024. The Land Department took 35 site photos at its inspections.
Is Greenway 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Greenway 2?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Greenway 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.