Greenway 2 construction progress
Greenway 2 in Dubai World Central is 34% built at the Land Department inspection of July 2026. Developer Emaar Dubai South Dwc. Completion registered for May 2028.
34%
Built, at the Land Department site inspection of 29 July 2026
Running behind its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- December 2028
- Construction started
- October 2024
- Registered with the Land Department
- June 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 492
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- غرين واي 2
- Land Department project number
- 3121
- Land Department site inspections
- 6
Schedule
Between October 2025 and July 2026 the site added about 2.3 points a month. At that rate it would finish around December 2028, more than three months after the May 2028 date registered with the Land Department.
Site inspections
29 July 2026
34%+10 pts
21 April 2026
24%+11 pts
16 October 2025
13%+8.6 pts
12 June 2025
4.4%+2.9 pts
16 December 2024
1.5%+1.5 pts
30 May 2024
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenway 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Greenway 2 be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Greenway 2 is built?
- 34%, measured at the Land Department site inspection on 29 July 2026. The Land Department engineers have inspected the site 6 times since May 2024.
- Is Greenway 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Greenway 2?
- The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenway 2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 30%.
- Golf PointAlso by Emaar Dubai South Dwc. 4.8%, Due October 2028.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.png&w=3840&q=75)