Greenway 2 construction progress

Greenway 2 in Dubai World Central is 34% built at the Land Department inspection of July 2026. Developer Emaar Dubai South Dwc. Completion registered for May 2028.

34%

Built, at the Land Department site inspection of 29 July 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
December 2028
Construction started
October 2024
Registered with the Land Department
June 2024
Units
492
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
غرين واي 2
Land Department project number
3121
Land Department site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 2.3 points a month. At that rate it would finish around December 2028, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 July 2026

34%+10 pts

  • Greenway 2 construction site, Land Department inspection photo 1, 29 July 2026
  • Greenway 2 construction site, Land Department inspection photo 2, 29 July 2026
  • Greenway 2 construction site, Land Department inspection photo 3, 29 July 2026
  • Greenway 2 construction site, Land Department inspection photo 4, 29 July 2026

21 April 2026

24%+11 pts

  • Greenway 2 construction site, Land Department inspection photo 1, 21 April 2026
  • Greenway 2 construction site, Land Department inspection photo 2, 21 April 2026
  • Greenway 2 construction site, Land Department inspection photo 3, 21 April 2026
  • Greenway 2 construction site, Land Department inspection photo 4, 21 April 2026

16 October 2025

13%+8.6 pts

  • Greenway 2 construction site, Land Department inspection photo 1, 16 October 2025
  • Greenway 2 construction site, Land Department inspection photo 2, 16 October 2025
  • Greenway 2 construction site, Land Department inspection photo 3, 16 October 2025
  • Greenway 2 construction site, Land Department inspection photo 4, 16 October 2025

12 June 2025

4.4%+2.9 pts

  • Greenway 2 construction site, Land Department inspection photo 1, 12 June 2025
  • Greenway 2 construction site, Land Department inspection photo 2, 12 June 2025
  • Greenway 2 construction site, Land Department inspection photo 3, 12 June 2025
  • Greenway 2 construction site, Land Department inspection photo 4, 12 June 2025

16 December 2024

1.5%+1.5 pts

  • Greenway 2 construction site, Land Department inspection photo 1, 16 December 2024
  • Greenway 2 construction site, Land Department inspection photo 2, 16 December 2024
  • Greenway 2 construction site, Land Department inspection photo 3, 16 December 2024

30 May 2024

0%

  • Greenway 2 construction site, Land Department inspection photo 1, 30 May 2024
  • Greenway 2 construction site, Land Department inspection photo 2, 30 May 2024
  • Greenway 2 construction site, Land Department inspection photo 3, 30 May 2024

All 35 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenway 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Greenway 2 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around December 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Greenway 2 is built?
34%, measured at the Land Department site inspection on 29 July 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is Greenway 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Greenway 2?
The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Greenway 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.