Expo City Mangrove Residences construction progress
Expo City Mangrove Residences in Dubai World Central is 91% built at the Land Department inspection of August 2026. Developer Expo City Mangrove Residences Development Fzco. Completion registered for January 2026.
91%
Built, at the Land Department site inspection of 18 August 2026
8 months past its registered completion date
- Completion date (Land Department)
- January 2026
- Finish at recent pace
- November 2026
- Construction started
- June 2023
- Registered with the Land Department
- April 2023
- Developer
- Expo City Mangrove Residences Development Fzco
- Community
- Dubai World Central
- Units
- 470
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- إكسبو سيتي مانجروف ريزيدنس
- Land Department project number
- 2612
- Land Department site inspections
- 9
Schedule
Expo City Mangrove Residences was registered to complete in January 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
18 August 2026
91%+8.9 pts
21 May 2026
82%+9.0 pts
3 April 2026
73%+8.2 pts
26 November 2025
65%+13 pts
22 August 2025
52%+25 pts
11 April 2025
27%+11 pts
6 December 2024
16%+15 pts
11 October 2023
1.6%+1.6 pts
17 March 2023
0%
Context
Dubai World Central has 51 projects under construction, 29% built on average.
Own a unit in Expo City Mangrove Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Expo City Mangrove Residences be completed?
- The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Expo City Mangrove Residences is built?
- 91%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 9 times since March 2023.
- Is Expo City Mangrove Residences delayed?
- Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
- Who is building Expo City Mangrove Residences?
- The registered developer is Expo City Mangrove Residences Development Fzco.
- Which bank holds the escrow account for Expo City Mangrove Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Azizi Venice 4Nearby in Dubai World Central. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

-.jpg&w=3840&q=75)
-.jpg&w=3840&q=75)
-.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)