Expo City Mangrove Residences construction progress
Expo City Mangrove Residences in Dubai World Central was registered to complete in January 2026 and is still under construction. At the last site inspection, in August 2026, it was 91% built. The developer is Expo City Mangrove Residences Development Fzco.
91%
Built, at the site inspection of 18 August 2026
10 months past its registered completion date
- Registered completion date
- January 2026
- Finish at recent pace
- November 2026
- Construction started
- June 2023
- First registered
- April 2023
- Developer
- Expo City Mangrove Residences Development Fzco
- Community
- Dubai World Central
- Units
- 470
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- إكسبو سيتي مانجروف ريزيدنس
- Project number
- 2612
- Site inspections
- 9
Schedule
Expo City Mangrove Residences was registered to complete in January 2026, 10 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
18 August 2026
91%+8.9 pts
21 May 2026
82%+9.0 pts
3 April 2026
73%+8.2 pts
26 November 2025
65%+13 pts
22 August 2025
52%+25 pts
11 April 2025
27%+11 pts
6 December 2024
16%+15 pts
11 October 2023
1.6%+1.6 pts
17 March 2023
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Own a unit in Expo City Mangrove Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Expo City Mangrove Residences handover date?
- The registered completion date was January 2026, and the register still lists Expo City Mangrove Residences as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Expo City Mangrove Residences?
- Expo City Mangrove Residences was 91% built at the site inspection on 18 August 2026. The site has been inspected 9 times since March 2023. The Land Department took 61 site photos at its inspections.
- Is Expo City Mangrove Residences delayed?
- Yes. Its registered completion date of January 2026 has passed and the project is still listed as under construction.
- Who is building Expo City Mangrove Residences?
- The registered developer is Expo City Mangrove Residences Development Fzco.
- Which bank holds the escrow account for Expo City Mangrove Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

-.jpg&w=3840&q=75)
-.jpg&w=3840&q=75)
-.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)