Greenridge construction progress

The registered completion date for Greenridge in Dubai World Central is December 2028. At the last site inspection, in June 2026, it was 36% built. The developer is Emaar Dubai South Dwc.

36%

Built, at the site inspection of 17 June 2026

On pace for its date

Registered completion date
December 2028
Finish at recent pace
March 2028
Construction started
January 2025
First registered
September 2024
Units
520
Escrow bank
Mashreq Bank
Name in Arabic
جرين ريدج
Project number
3283
Site inspections
6

Schedule

Since July 2025 Greenridge has added about 3.0 points a month. That puts 100% around March 2028, within three months of its registered completion date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 June 2026

36%+9.2 pts

  • Greenridge construction site, inspection photo 1, 17 June 2026
  • Greenridge construction site, inspection photo 2, 17 June 2026
  • Greenridge construction site, inspection photo 3, 17 June 2026
  • Greenridge construction site, inspection photo 4, 17 June 2026

9 February 2026

26%+21 pts

  • Greenridge construction site, inspection photo 1, 9 February 2026
  • Greenridge construction site, inspection photo 2, 9 February 2026
  • Greenridge construction site, inspection photo 3, 9 February 2026
  • Greenridge construction site, inspection photo 4, 9 February 2026

29 October 2025

5.6%+4.6 pts

  • Greenridge construction site, inspection photo 1, 29 October 2025
  • Greenridge construction site, inspection photo 2, 29 October 2025
  • Greenridge construction site, inspection photo 3, 29 October 2025
  • Greenridge construction site, inspection photo 4, 29 October 2025

1 July 2025

1.0%+0.3 pts

  • Greenridge construction site, inspection photo 1, 1 July 2025
  • Greenridge construction site, inspection photo 2, 1 July 2025
  • Greenridge construction site, inspection photo 3, 1 July 2025
  • Greenridge construction site, inspection photo 4, 1 July 2025

20 March 2025

0.7%+0.7 pts

  • Greenridge construction site, inspection photo 1, 20 March 2025
  • Greenridge construction site, inspection photo 2, 20 March 2025
  • Greenridge construction site, inspection photo 3, 20 March 2025
  • Greenridge construction site, inspection photo 4, 20 March 2025

9 September 2024

0%

  • Greenridge construction site, inspection photo 1, 9 September 2024
  • Greenridge construction site, inspection photo 2, 9 September 2024

All 33 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenridge?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Greenridge handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Greenridge?
Greenridge was 36% built at the site inspection on 17 June 2026. The site has been inspected 6 times since September 2024. The Land Department took 33 site photos at its inspections.
Is Greenridge delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2028.
Who is building Greenridge?
The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Greenridge?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.