Greenridge construction progress
The registered completion date for Greenridge in Dubai World Central is December 2028. At the last site inspection, in June 2026, it was 36% built. The developer is Emaar Dubai South Dwc.
36%
Built, at the site inspection of 17 June 2026
On pace for its date
- Registered completion date
- December 2028
- Finish at recent pace
- March 2028
- Construction started
- January 2025
- First registered
- September 2024
- Developer
- Emaar Dubai South Dwc
- Community
- Dubai World Central
- Units
- 520
- Escrow bank
- Mashreq Bank
- Name in Arabic
- جرين ريدج
- Project number
- 3283
- Site inspections
- 6
Schedule
Since July 2025 Greenridge has added about 3.0 points a month. That puts 100% around March 2028, within three months of its registered completion date of December 2028.
Site inspections
17 June 2026
36%+9.2 pts
9 February 2026
26%+21 pts
29 October 2025
5.6%+4.6 pts
1 July 2025
1.0%+0.3 pts
20 March 2025
0.7%+0.7 pts
9 September 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenridge?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Greenridge handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Greenridge?
- Greenridge was 36% built at the site inspection on 17 June 2026. The site has been inspected 6 times since September 2024. The Land Department took 33 site photos at its inspections.
- Is Greenridge delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2028.
- Who is building Greenridge?
- The registered developer is Emaar Dubai South Dwc. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenridge?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 2Also by Emaar Dubai South Dwc. 92%, Due December 2026.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 57%.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Azizi Venice 3Nearby in Dubai World Central. 76%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)