Azizi Venice 11 construction progress

The registered completion date for Azizi Venice 11 in Dubai World Central is August 2027. At the last site inspection, in September 2026, it was 26% built. The developer is Azizi Developments.

26%

Built, at the site inspection of 9 September 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
December 2029
Construction started
August 2024
First registered
September 2024
Units
1,094
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزى فينيس 11
Project number
3239
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.9 points a month. At that rate it would finish around December 2029, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 September 2026

26%+12 pts

  • Azizi Venice 11 construction site, inspection photo 1, 9 September 2026
  • Azizi Venice 11 construction site, inspection photo 2, 9 September 2026
  • Azizi Venice 11 construction site, inspection photo 3, 9 September 2026
  • Azizi Venice 11 construction site, inspection photo 4, 9 September 2026

4 March 2026

14%+14 pts

  • Azizi Venice 11 construction site, inspection photo 1, 4 March 2026
  • Azizi Venice 11 construction site, inspection photo 2, 4 March 2026
  • Azizi Venice 11 construction site, inspection photo 3, 4 March 2026
  • Azizi Venice 11 construction site, inspection photo 4, 4 March 2026

15 August 2024

0%

  • Azizi Venice 11 construction site, inspection photo 1, 15 August 2024
  • Azizi Venice 11 construction site, inspection photo 2, 15 August 2024

All 16 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Venice 11?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Venice 11 handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Venice 11?
Azizi Venice 11 was 26% built at the site inspection on 9 September 2026. The site has been inspected 3 times since August 2024. The Land Department took 16 site photos at its inspections.
Is Azizi Venice 11 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Azizi Venice 11?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 11?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.