Azizi Venice 11 construction progress
The registered completion date for Azizi Venice 11 in Dubai World Central is August 2027. At the last site inspection, in September 2026, it was 26% built. The developer is Azizi Developments.
26%
Built, at the site inspection of 9 September 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- December 2029
- Construction started
- August 2024
- First registered
- September 2024
- Developer
- Azizi Developments
- Community
- Dubai World Central
- Units
- 1,094
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- عزيزى فينيس 11
- Project number
- 3239
- Site inspections
- 3
Schedule
Between March 2026 and September 2026 the site added about 1.9 points a month. At that rate it would finish around December 2029, more than three months after its registered date of August 2027.
Site inspections
9 September 2026
26%+12 pts
4 March 2026
14%+14 pts
15 August 2024
0%
Context
Dubai World Central has 53 projects under construction, 31% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Venice 11?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Venice 11 handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Venice 11?
- Azizi Venice 11 was 26% built at the site inspection on 9 September 2026. The site has been inspected 3 times since August 2024. The Land Department took 16 site photos at its inspections.
- Is Azizi Venice 11 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Azizi Venice 11?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Venice 11?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Fairway Villas 2Nearby in Dubai World Central. 92%, Due December 2026.
- Expo City Mangrove ResidencesNearby in Dubai World Central. 91%, Due January 2026, passed.
- Expo City Sky ResidencesNearby in Dubai World Central. 53%.
- Expo City ValleyNearby in Dubai World Central. 66%, Due January 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)