Azizi Venice 11 construction progress

Azizi Venice 11 in Dubai World Central is 26% built at the Land Department inspection of September 2026. Developer Azizi Developments. Completion registered for August 2027.

26%

Built, at the Land Department site inspection of 9 September 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
December 2029
Construction started
August 2024
Registered with the Land Department
September 2024
Units
1,094
Escrow bank
Dubai Islamic Bank
Name in Arabic
عزيزى فينيس 11
Land Department project number
3239
Land Department site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.9 points a month. At that rate it would finish around December 2029, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2026

26%+12 pts

  • Azizi Venice 11 construction site, Land Department inspection photo 1, 9 September 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 2, 9 September 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 3, 9 September 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 4, 9 September 2026

4 March 2026

14%+14 pts

  • Azizi Venice 11 construction site, Land Department inspection photo 1, 4 March 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 2, 4 March 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 3, 4 March 2026
  • Azizi Venice 11 construction site, Land Department inspection photo 4, 4 March 2026

15 August 2024

0%

  • Azizi Venice 11 construction site, Land Department inspection photo 1, 15 August 2024
  • Azizi Venice 11 construction site, Land Department inspection photo 2, 15 August 2024

All 16 site photos, by inspection date

Context

Dubai World Central has 51 projects under construction, 29% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Venice 11?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Venice 11 be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around December 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Venice 11 is built?
26%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 3 times since August 2024.
Is Azizi Venice 11 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Azizi Venice 11?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Venice 11?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.