Azizi Developments projects under construction
Azizi Developments has 56 projects under construction in Dubai. On average they are 31% built. 10 have passed their registered completion date. The next one due is Azizi Riviera 62, in March 2027.
- Azizi Riviera 62Meydan One Community93%Due March 2027
- Azizi Riviera 64Meydan One Community92%Due May 2027
- Azizi Riviera 66Meydan One Community91%Due May 2027
- Azizi GrandDubai Sports City82%Due February 2025, passed
- Azizi ZainAl Furjan80%Due October 2027
- Azizi Riviera ReveMeydan One Community77%Due February 2025, passed
- Azizi Venice 3Dubai World Central76%Due December 2025, passed
- Adeba AziziDubai Health Care City Phase 275%No date set
- Azizi Riviera 54Meydan One Community75%Due May 2027
- Azizi Riviera 68Meydan One Community75%Due May 2027
- Azizi Venice 1Dubai World Central67%Due December 2025, passed
- Azizi Venice 5Dubai World Central63%Due October 2025, passed
- Azizi Riviera 53Meydan One Community63%Due March 2027
- Azizi Venice 4Dubai World Central62%Due December 2025, passed
- Azizi Riviera 50Meydan One Community61%Due March 2027
- Azizi Venice 2Dubai World Central57%Due December 2025, passed
- Beach Oasis 2Dubai Studio City57%Due April 2026, passed
- Azizi Riviera 49Meydan One Community54%Due March 2027
- Azizi Venice 9Dubai World Central54%No date set
- Azizi Venice 8Dubai World Central53%No date set
- Azizi Venice 13Dubai World Central46%Due September 2027
- Azizi JewelAl Furjan43%No date set
- Azizi NeilaAl Furjan39%Due July 2027
- Azizi Venice 10Dubai World Central36%No date set
- Azizi Venice 14Dubai World Central30%Due May 2026, passed
- Azizi Venice 7Dubai World Central29%Due January 2026, passed
- Azizi Venice 6Dubai World Central27%Due December 2027
- Azizi Venice 11Dubai World Central26%Due August 2027
- Azizi Venice 12Dubai World Central22%Due September 2027
- Burj AziziTrade Center First7.5%Due August 2030
- Azizi RubyJumeirah Village Circle4.1%Due January 2028
- Azizi Venice 16Dubai World Central3.7%Due June 2027
- Azizi Venice 15Dubai World Central3.3%Due May 2027
- Azizi SikanderAl Furjan3.2%Due June 2027
- Azizi EmeraldDubai Health Care City Phase 13.0%Due February 2028
- Raffi By AziziAl Furjan2.8%Due January 2028
- Azizi Lina2.4%Due September 2028
- Azizi AmirAl Furjan2.4%Due June 2027
- Azizi Noura2.1%Due July 2028
- Arian By AziziDown Town Jabal Ali2.0%Due January 2028
- Azizi AbrahamDown Town Jabal Ali2.0%Due August 2027
- Azizi DavidSama Al Jadaf2.0%Due September 2028
- Azizi Leily2.0%Due September 2028
- Azizi WaresDown Town Jabal Ali2.0%Due March 2028
- Wasl By AziziPalm Deira2.0%Due February 2028
- Azizi Gabriel1.1%Due July 2028
- Azizi Milan 18City Of Arabia0%Due April 2027
- Azizi Milan 20City Of Arabia0%Due April 2027
- Azizi Milan 28City Of Arabia0%Due June 2027
- Azizi Milan 30City Of Arabia0%Due April 2027
- Azizi Milan 51City Of Arabia0%Due March 2027
- Azizi Milan 53City Of Arabia0%Due April 2027
- Azizi Milan 55City Of Arabia0%Due April 2027
- Azizi Milan 9Wadi Al Safa 40%Due May 2027
- Azizi Milan HeightsCity Of Arabia0%Due September 2028
- Azizi Rose0%Due July 2028
Questions
How many projects is Azizi Developments building in Dubai?
56 projects are under construction, 31% built on average at the latest site inspections.
Which Azizi Developments projects finish next?
By registered completion date: Azizi Riviera 62 (March 2027, 93% built), Azizi Riviera 53 (March 2027, 63% built) and Azizi Riviera 50 (March 2027, 61% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Azizi Developments projects delayed?
10 of its 56 projects have passed the registered completion date, among them Azizi Grand, Azizi Riviera Reve and Azizi Venice 5. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Azizi Developments building?
Its projects are in Dubai World Central (16), Meydan One Community (9) and City Of Arabia (8), and 11 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.