Azizi Riviera 54 construction progress
Azizi Riviera 54 in Meydan One Community is 75% built at the Land Department inspection of August 2026. Developer Azizi Developments. Completion registered for May 2027.
75%
Built, at the Land Department site inspection of 7 August 2026
On pace for its date
- Completion date (Land Department)
- May 2027
- Finish at recent pace
- May 2027
- Construction started
- May 2025
- Registered with the Land Department
- June 2025
- Developer
- Azizi Developments
- Community
- Meydan One Community
- Units
- 203
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- عزيزي ريفيرا 54
- Land Department project number
- 3739
- Land Department site inspections
- 4
Schedule
Since August 2025 Azizi Riviera 54 has added about 2.8 points a month. That puts 100% around May 2027, within three months of its registered completion date of May 2027.
Site inspections
7 August 2026
75%+15 pts
21 January 2026
60%+19 pts
16 August 2025
41%+6.7 pts
16 May 2025
35%
Context
Meydan One Community has 10 projects under construction, 77% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Riviera 54?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Riviera 54 be completed?
- The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Riviera 54 is built?
- 75%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 4 times since May 2025.
- Is Azizi Riviera 54 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
- Who is building Azizi Riviera 54?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Riviera 54?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)