Azizi Sikander construction progress

Azizi Sikander in Al Furjan is 2.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for June 2027.

2.0%

Built, at the Land Department site inspection of 18 March 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
September 2062
Construction started
June 2025
Registered with the Land Department
July 2025
Community
Al Furjan
Units
226
Escrow bank
Ajman Bank
Name in Arabic
عزيزي سكندر
Land Department project number
3845
Land Department site inspections
2

Schedule

Between June 2025 and March 2026 the site added about 0.2 points a month. At that rate it would finish around September 2062, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 March 2026

2.0%+2.0 pts

  • Azizi Sikander construction site, Land Department inspection photo 1, 18 March 2026
  • Azizi Sikander construction site, Land Department inspection photo 2, 18 March 2026
  • Azizi Sikander construction site, Land Department inspection photo 3, 18 March 2026
  • Azizi Sikander construction site, Land Department inspection photo 4, 18 March 2026

19 June 2025

0%

  • Azizi Sikander construction site, Land Department inspection photo 1, 19 June 2025
  • Azizi Sikander construction site, Land Department inspection photo 2, 19 June 2025

All 6 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Sikander?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Sikander be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around September 2062. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Sikander is built?
2.0%, measured at the Land Department site inspection on 18 March 2026. The Land Department engineers have inspected the site 2 times since June 2025.
Is Azizi Sikander delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Azizi Sikander?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Sikander?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.