Azizi Sikander construction progress
The registered completion date for Azizi Sikander in Al Furjan is June 2027. At the last site inspection, in November 2026, it was 3.2% built. The developer is Azizi Developments.
3.2%
Built, at the site inspection of 18 November 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- December 2081
- Construction started
- June 2025
- First registered
- July 2025
- Developer
- Azizi Developments
- Community
- Al Furjan
- Units
- 226
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي سكندر
- Project number
- 3845
- Site inspections
- 3
Schedule
Between March 2026 and November 2026 the site added about 0.1 points a month. At that rate it would finish around December 2081, more than three months after its registered date of June 2027.
Site inspections
18 November 2026
3.2%+1.2 pts
18 March 2026
2.0%+2.0 pts
19 June 2025
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Sikander?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Sikander handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2081. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Sikander?
- Azizi Sikander was 3.2% built at the site inspection on 18 November 2026. The site has been inspected 3 times since June 2025. The Land Department took 10 site photos at its inspections.
- Is Azizi Sikander delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Azizi Sikander?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Sikander?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.