Beach Oasis 2 construction progress

Beach Oasis 2 in Dubai Studio City was registered to complete in April 2026 and is still under construction. At the last site inspection, in November 2026, it was 57% built. The developer is Azizi Developments.

57%

Built, at the site inspection of 23 November 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
December 2028
Construction started
April 2024
First registered
August 2024
Units
704
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
بيتش اويسيس 2
Project number
3043
Site inspections
5

Schedule

Beach Oasis 2 was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around December 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 November 2026

57%+3.8 pts

  • Beach Oasis 2 construction site, inspection photo 1, 23 November 2026
  • Beach Oasis 2 construction site, inspection photo 2, 23 November 2026
  • Beach Oasis 2 construction site, inspection photo 3, 23 November 2026
  • Beach Oasis 2 construction site, inspection photo 4, 23 November 2026

7 September 2026

53%+13 pts

  • Beach Oasis 2 construction site, inspection photo 1, 7 September 2026
  • Beach Oasis 2 construction site, inspection photo 2, 7 September 2026
  • Beach Oasis 2 construction site, inspection photo 3, 7 September 2026
  • Beach Oasis 2 construction site, inspection photo 4, 7 September 2026

3 February 2026

41%+34 pts

  • Beach Oasis 2 construction site, inspection photo 1, 3 February 2026
  • Beach Oasis 2 construction site, inspection photo 2, 3 February 2026
  • Beach Oasis 2 construction site, inspection photo 3, 3 February 2026
  • Beach Oasis 2 construction site, inspection photo 4, 3 February 2026

15 July 2025

6.3%+6.3 pts

  • Beach Oasis 2 construction site, inspection photo 1, 15 July 2025
  • Beach Oasis 2 construction site, inspection photo 2, 15 July 2025
  • Beach Oasis 2 construction site, inspection photo 3, 15 July 2025
  • Beach Oasis 2 construction site, inspection photo 4, 15 July 2025

24 April 2024

0%

  • Beach Oasis 2 construction site, inspection photo 1, 24 April 2024
  • Beach Oasis 2 construction site, inspection photo 2, 24 April 2024
  • Beach Oasis 2 construction site, inspection photo 3, 24 April 2024

All 39 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Beach Oasis 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Beach Oasis 2 handover date?
The registered completion date was April 2026, and the register still lists Beach Oasis 2 as under construction. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Beach Oasis 2?
Beach Oasis 2 was 57% built at the site inspection on 23 November 2026. The site has been inspected 5 times since April 2024. The Land Department took 39 site photos at its inspections.
Is Beach Oasis 2 delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Beach Oasis 2?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Oasis 2?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.