Azizi Emerald construction progress

Azizi Emerald in Dubai Health Care City Phase 1 is 3.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for February 2028.

3.0%

Built, at the Land Department site inspection of 24 March 2026

Running behind its date

Completion date (Land Department)
February 2028
Finish at recent pace
May 2060
Construction started
February 2025
Registered with the Land Department
April 2025
Community
Dubai Health Care City Phase 1
Units
102
Escrow bank
Commercial Bank of Dubai
Name in Arabic
عزيزي ايمرالد
Land Department project number
3566
Land Department site inspections
2

Schedule

Between March 2025 and March 2026 the site added about 0.2 points a month. At that rate it would finish around May 2060, more than three months after the February 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 March 2026

3.0%+3.0 pts

  • Azizi Emerald construction site, Land Department inspection photo 1, 24 March 2026
  • Azizi Emerald construction site, Land Department inspection photo 2, 24 March 2026
  • Azizi Emerald construction site, Land Department inspection photo 3, 24 March 2026
  • Azizi Emerald construction site, Land Department inspection photo 4, 24 March 2026

3 March 2025

0%

  • Azizi Emerald construction site, Land Department inspection photo 1, 3 March 2025
  • Azizi Emerald construction site, Land Department inspection photo 2, 3 March 2025

All 9 site photos, by inspection date

Context

Dubai Health Care City Phase 1 has 2 projects under construction, 7.2% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Emerald?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Emerald be completed?
The completion date registered with the Dubai Land Department is February 2028. At the pace of its recent inspections the site would reach 100% around May 2060. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Emerald is built?
3.0%, measured at the Land Department site inspection on 24 March 2026. The Land Department engineers have inspected the site 2 times since March 2025.
Is Azizi Emerald delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Azizi Emerald?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Emerald?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.