Azizi Emerald construction progress
Azizi Emerald in Dubai Health Care City Phase 1 is 3.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for February 2028.
3.0%
Built, at the Land Department site inspection of 24 March 2026
Running behind its date
- Completion date (Land Department)
- February 2028
- Finish at recent pace
- May 2060
- Construction started
- February 2025
- Registered with the Land Department
- April 2025
- Developer
- Azizi Developments
- Community
- Dubai Health Care City Phase 1
- Units
- 102
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- عزيزي ايمرالد
- Land Department project number
- 3566
- Land Department site inspections
- 2
Schedule
Between March 2025 and March 2026 the site added about 0.2 points a month. At that rate it would finish around May 2060, more than three months after the February 2028 date registered with the Land Department.
Site inspections
24 March 2026
3.0%+3.0 pts
3 March 2025
0%
Context
Dubai Health Care City Phase 1 has 2 projects under construction, 7.2% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Emerald?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Emerald be completed?
- The completion date registered with the Dubai Land Department is February 2028. At the pace of its recent inspections the site would reach 100% around May 2060. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Emerald is built?
- 3.0%, measured at the Land Department site inspection on 24 March 2026. The Land Department engineers have inspected the site 2 times since March 2025.
- Is Azizi Emerald delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Azizi Emerald?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Emerald?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- LuminaNearby in Dubai Health Care City Phase 1. 11%, Due April 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.