Azizi Emerald construction progress

The registered completion date for Azizi Emerald in Dubai Health Care City Phase 1 is February 2028. At the last site inspection, in November 2026, it was 3.0% built. The developer is Azizi Developments.

3.0%

Built, at the site inspection of 17 November 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
May 3606
Construction started
February 2025
First registered
April 2025
Community
Dubai Health Care City Phase 1
Units
102
Escrow bank
Commercial Bank of Dubai
Name in Arabic
عزيزي ايمرالد
Project number
3566
Site inspections
3

Schedule

Between March 2026 and November 2026 the site added about 0.0 points a month. At that rate it would finish around May 3606, more than three months after its registered date of February 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2026

3.0%+0.0 pts

  • Azizi Emerald construction site, inspection photo 1, 17 November 2026
  • Azizi Emerald construction site, inspection photo 2, 17 November 2026
  • Azizi Emerald construction site, inspection photo 3, 17 November 2026
  • Azizi Emerald construction site, inspection photo 4, 17 November 2026

24 March 2026

3.0%+3.0 pts

  • Azizi Emerald construction site, inspection photo 1, 24 March 2026
  • Azizi Emerald construction site, inspection photo 2, 24 March 2026
  • Azizi Emerald construction site, inspection photo 3, 24 March 2026
  • Azizi Emerald construction site, inspection photo 4, 24 March 2026

3 March 2025

0%

  • Azizi Emerald construction site, inspection photo 1, 3 March 2025
  • Azizi Emerald construction site, inspection photo 2, 3 March 2025

All 16 site photos, by inspection date

Context

Dubai Health Care City Phase 1 has 2 projects under construction, 7.2% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Emerald?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Emerald handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 3606. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Emerald?
Azizi Emerald was 3.0% built at the site inspection on 17 November 2026. The site has been inspected 3 times since March 2025. The Land Department took 16 site photos at its inspections.
Is Azizi Emerald delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Azizi Emerald?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Emerald?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.