Azizi Emerald construction progress
The registered completion date for Azizi Emerald in Dubai Health Care City Phase 1 is February 2028. At the last site inspection, in November 2026, it was 3.0% built. The developer is Azizi Developments.
3.0%
Built, at the site inspection of 17 November 2026
Running behind its date
- Registered completion date
- February 2028
- Finish at recent pace
- May 3606
- Construction started
- February 2025
- First registered
- April 2025
- Developer
- Azizi Developments
- Community
- Dubai Health Care City Phase 1
- Units
- 102
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- عزيزي ايمرالد
- Project number
- 3566
- Site inspections
- 3
Schedule
Between March 2026 and November 2026 the site added about 0.0 points a month. At that rate it would finish around May 3606, more than three months after its registered date of February 2028.
Site inspections
17 November 2026
3.0%+0.0 pts
24 March 2026
3.0%+3.0 pts
3 March 2025
0%
Context
Dubai Health Care City Phase 1 has 2 projects under construction, 7.2% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Emerald?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Emerald handover date?
- The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 3606. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Emerald?
- Azizi Emerald was 3.0% built at the site inspection on 17 November 2026. The site has been inspected 3 times since March 2025. The Land Department took 16 site photos at its inspections.
- Is Azizi Emerald delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Azizi Emerald?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Emerald?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- LuminaNearby in Dubai Health Care City Phase 1. 11%, Due April 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.