Azizi Wares construction progress

Azizi Wares in Down Town Jabal Ali is 2.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for March 2028.

2.0%

Built, at the Land Department site inspection of 18 March 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
May 2052
Construction started
March 2026
Registered with the Land Department
April 2026
Units
336
Escrow bank
Ajman Bank
Name in Arabic
عزيزي ويرز
Land Department project number
4076
Land Department site inspections
2

Schedule

Between September 2025 and March 2026 the site added about 0.3 points a month. At that rate it would finish around May 2052, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 March 2026

2.0%+2.0 pts

  • Azizi Wares construction site, Land Department inspection photo 1, 18 March 2026
  • Azizi Wares construction site, Land Department inspection photo 2, 18 March 2026
  • Azizi Wares construction site, Land Department inspection photo 3, 18 March 2026

4 September 2025

0%

  • Azizi Wares construction site, Land Department inspection photo 1, 4 September 2025
  • Azizi Wares construction site, Land Department inspection photo 2, 4 September 2025

All 5 site photos, by inspection date

Context

Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Wares?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Wares be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around May 2052. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Wares is built?
2.0%, measured at the Land Department site inspection on 18 March 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Azizi Wares delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Azizi Wares?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Wares?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.