Azizi Lina construction progress
The registered completion date for Azizi Lina is September 2028. At the last site inspection, in November 2026, it was 2.4% built. The developer is Azizi Developments.
2.4%
Built, at the site inspection of 16 November 2026
Running behind its date
- Registered completion date
- September 2028
- Finish at recent pace
- April 2207
- Construction started
- February 2026
- First registered
- April 2026
- Developer
- Azizi Developments
- Units
- 242
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي لينا
- Project number
- 4141
- Site inspections
- 3
Schedule
Between March 2026 and November 2026 the site added about 0.0 points a month. At that rate it would finish around April 2207, more than three months after its registered date of September 2028.
Site inspections
16 November 2026
2.4%+0.4 pts
18 March 2026
2.0%+2.0 pts
14 October 2025
0%
Context
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Lina?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Lina handover date?
- The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2207. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Lina?
- Azizi Lina was 2.4% built at the site inspection on 16 November 2026. The site has been inspected 3 times since October 2025. The Land Department took 11 site photos at its inspections.
- Is Azizi Lina delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Azizi Lina?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Lina?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.