Azizi Lina construction progress
Azizi Lina is 2.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for September 2028.
2.0%
Built, at the Land Department site inspection of 18 March 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- January 2047
- Construction started
- February 2026
- Registered with the Land Department
- April 2026
- Developer
- Azizi Developments
- Units
- 242
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي لينا
- Land Department project number
- 4141
- Land Department site inspections
- 2
Schedule
Between October 2025 and March 2026 the site added about 0.4 points a month. At that rate it would finish around January 2047, more than three months after the September 2028 date registered with the Land Department.
Site inspections
18 March 2026
2.0%+2.0 pts
14 October 2025
0%
Context
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Lina?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Azizi Lina be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around January 2047. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Lina is built?
- 2.0%, measured at the Land Department site inspection on 18 March 2026. The Land Department engineers have inspected the site 2 times since October 2025.
- Is Azizi Lina delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Azizi Lina?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Lina?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.png&w=3840&q=75)
.png&w=3840&q=75)