Skip to content

Azizi Lina construction progress

The registered completion date for Azizi Lina is September 2028. At the last site inspection, in November 2026, it was 2.4% built. The developer is Azizi Developments.

2.4%

Built, at the site inspection of 16 November 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
April 2207
Construction started
February 2026
First registered
April 2026
Units
242
Escrow bank
Ajman Bank
Name in Arabic
عزيزي لينا
Project number
4141
Site inspections
3

Schedule

Between March 2026 and November 2026 the site added about 0.0 points a month. At that rate it would finish around April 2207, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

2.4%+0.4 pts

  • Azizi Lina construction site, inspection photo 1, 16 November 2026
  • Azizi Lina construction site, inspection photo 2, 16 November 2026
  • Azizi Lina construction site, inspection photo 3, 16 November 2026
  • Azizi Lina construction site, inspection photo 4, 16 November 2026

18 March 2026

2.0%+2.0 pts

  • Azizi Lina construction site, inspection photo 1, 18 March 2026
  • Azizi Lina construction site, inspection photo 2, 18 March 2026

14 October 2025

0%

  • Azizi Lina construction site, inspection photo 1, 14 October 2025
  • Azizi Lina construction site, inspection photo 2, 14 October 2025

All 11 site photos, by inspection date

Context

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Lina?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Lina handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2207. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Lina?
Azizi Lina was 2.4% built at the site inspection on 16 November 2026. The site has been inspected 3 times since October 2025. The Land Department took 11 site photos at its inspections.
Is Azizi Lina delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Azizi Lina?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Lina?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.