Azizi Neila construction progress

Azizi Neila in Al Furjan is 39% built at the Land Department inspection of October 2026. Developer Azizi Developments. Completion registered for July 2027.

39%

Built, at the Land Department site inspection of 5 October 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
September 2028
Construction started
July 2024
Registered with the Land Department
September 2024
Community
Al Furjan
Units
274
Escrow bank
First Abu Dhabi Bank
Name in Arabic
عزيزى نايلا
Land Department project number
3203
Land Department site inspections
4

Schedule

Between December 2025 and October 2026 the site added about 2.7 points a month. At that rate it would finish around September 2028, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 October 2026

39%+21 pts

  • Azizi Neila construction site, Land Department inspection photo 1, 5 October 2026
  • Azizi Neila construction site, Land Department inspection photo 2, 5 October 2026
  • Azizi Neila construction site, Land Department inspection photo 3, 5 October 2026
  • Azizi Neila construction site, Land Department inspection photo 4, 5 October 2026

13 April 2026

17%+4.9 pts

  • Azizi Neila construction site, Land Department inspection photo 1, 13 April 2026
  • Azizi Neila construction site, Land Department inspection photo 2, 13 April 2026
  • Azizi Neila construction site, Land Department inspection photo 3, 13 April 2026
  • Azizi Neila construction site, Land Department inspection photo 4, 13 April 2026

9 December 2025

12%+12 pts

  • Azizi Neila construction site, Land Department inspection photo 1, 9 December 2025
  • Azizi Neila construction site, Land Department inspection photo 2, 9 December 2025
  • Azizi Neila construction site, Land Department inspection photo 3, 9 December 2025
  • Azizi Neila construction site, Land Department inspection photo 4, 9 December 2025

20 August 2024

0%

  • Azizi Neila construction site, Land Department inspection photo 1, 20 August 2024
  • Azizi Neila construction site, Land Department inspection photo 2, 20 August 2024

All 21 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. Azizi Neila is ahead of that average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Neila?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Azizi Neila be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around September 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Neila is built?
39%, measured at the Land Department site inspection on 5 October 2026. The Land Department engineers have inspected the site 4 times since August 2024.
Is Azizi Neila delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Azizi Neila?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Neila?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.