Azizi Neila construction progress

The registered completion date for Azizi Neila in Al Furjan is July 2027. At the last site inspection, in October 2026, it was 39% built. The developer is Azizi Developments.

39%

Built, at the site inspection of 5 October 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
September 2028
Construction started
July 2024
First registered
September 2024
Community
Al Furjan
Units
274
Escrow bank
First Abu Dhabi Bank
Name in Arabic
عزيزى نايلا
Project number
3203
Site inspections
4

Schedule

Between December 2025 and October 2026 the site added about 2.7 points a month. At that rate it would finish around September 2028, more than three months after its registered date of July 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

39%+21 pts

  • Azizi Neila construction site, inspection photo 1, 5 October 2026
  • Azizi Neila construction site, inspection photo 2, 5 October 2026
  • Azizi Neila construction site, inspection photo 3, 5 October 2026
  • Azizi Neila construction site, inspection photo 4, 5 October 2026

13 April 2026

17%+4.9 pts

  • Azizi Neila construction site, inspection photo 1, 13 April 2026
  • Azizi Neila construction site, inspection photo 2, 13 April 2026
  • Azizi Neila construction site, inspection photo 3, 13 April 2026
  • Azizi Neila construction site, inspection photo 4, 13 April 2026

9 December 2025

12%+12 pts

  • Azizi Neila construction site, inspection photo 1, 9 December 2025
  • Azizi Neila construction site, inspection photo 2, 9 December 2025
  • Azizi Neila construction site, inspection photo 3, 9 December 2025
  • Azizi Neila construction site, inspection photo 4, 9 December 2025

20 August 2024

0%

  • Azizi Neila construction site, inspection photo 1, 20 August 2024
  • Azizi Neila construction site, inspection photo 2, 20 August 2024

All 21 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Neila?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Neila handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Neila?
Azizi Neila was 39% built at the site inspection on 5 October 2026. The site has been inspected 4 times since August 2024. The Land Department took 21 site photos at its inspections.
Is Azizi Neila delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Azizi Neila?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Neila?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.