Skip to content

Azizi Riviera 64 construction progress

Azizi Riviera 64 in Meydan One Community is 84% built at the Land Department inspection of September 2026. Developer Azizi Developments. Completion registered for May 2027.

84%

Built, at the Land Department site inspection of 7 September 2026

On pace for its date

Completion date (Land Department)
May 2027
Finish at recent pace
April 2027
Construction started
May 2025
Registered with the Land Department
August 2025
Units
127
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 64
Land Department project number
3794
Land Department site inspections
3

Schedule

Since January 2026 Azizi Riviera 64 has added about 2.3 points a month. That puts 100% around April 2027, within three months of its registered completion date of May 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 September 2026

84%+17 pts

  • Azizi Riviera 64 construction site, Land Department inspection photo 1, 7 September 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 2, 7 September 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 3, 7 September 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 4, 7 September 2026

28 January 2026

67%+26 pts

  • Azizi Riviera 64 construction site, Land Department inspection photo 1, 28 January 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 2, 28 January 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 3, 28 January 2026
  • Azizi Riviera 64 construction site, Land Department inspection photo 4, 28 January 2026

18 June 2025

41%

  • Azizi Riviera 64 construction site, Land Department inspection photo 1, 18 June 2025
  • Azizi Riviera 64 construction site, Land Department inspection photo 2, 18 June 2025
  • Azizi Riviera 64 construction site, Land Department inspection photo 3, 18 June 2025
  • Azizi Riviera 64 construction site, Land Department inspection photo 4, 18 June 2025

All 25 site photos, by inspection date

Context

Meydan One Community has 10 projects under construction, 77% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Riviera 64?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Riviera 64 be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Riviera 64 is built?
84%, measured at the Land Department site inspection on 7 September 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is Azizi Riviera 64 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
Who is building Azizi Riviera 64?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 64?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.