Azizi Riviera 64 construction progress

The registered completion date for Azizi Riviera 64 in Meydan One Community is May 2027. At the last site inspection, in September 2026, it was 84% built. The developer is Azizi Developments.

92%

Built, at the site inspection of 7 September 2026

On pace for its date

Registered completion date
May 2027
Finish at recent pace
April 2027
Construction started
May 2025
First registered
August 2025
Units
127
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 64
Project number
3794
Site inspections
3

Schedule

Since January 2026 Azizi Riviera 64 has added about 2.3 points a month. That puts 100% around April 2027, within three months of its registered completion date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 September 2026

84%+17 pts

  • Azizi Riviera 64 construction site, inspection photo 1, 7 September 2026
  • Azizi Riviera 64 construction site, inspection photo 2, 7 September 2026
  • Azizi Riviera 64 construction site, inspection photo 3, 7 September 2026
  • Azizi Riviera 64 construction site, inspection photo 4, 7 September 2026

28 January 2026

67%+26 pts

  • Azizi Riviera 64 construction site, inspection photo 1, 28 January 2026
  • Azizi Riviera 64 construction site, inspection photo 2, 28 January 2026
  • Azizi Riviera 64 construction site, inspection photo 3, 28 January 2026
  • Azizi Riviera 64 construction site, inspection photo 4, 28 January 2026

18 June 2025

41%

  • Azizi Riviera 64 construction site, inspection photo 1, 18 June 2025
  • Azizi Riviera 64 construction site, inspection photo 2, 18 June 2025
  • Azizi Riviera 64 construction site, inspection photo 3, 18 June 2025
  • Azizi Riviera 64 construction site, inspection photo 4, 18 June 2025

All 25 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 64?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 64 handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Riviera 64?
Azizi Riviera 64 was 92% built at the site inspection on 7 September 2026. The site has been inspected 3 times since June 2025. The Land Department took 25 site photos at its inspections.
Is Azizi Riviera 64 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2027.
Who is building Azizi Riviera 64?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 64?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.