Burj Azizi construction progress

The registered completion date for Burj Azizi in Trade Center First is August 2030. At the last site inspection, in September 2026, it was 7.5% built. The developer is Azizi Developments.

7.5%

Built, at the site inspection of 3 September 2026

Running behind its date

Registered completion date
August 2030
Finish at recent pace
June 2053
Construction started
August 2024
First registered
September 2024
Units
1,072
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج عزيزى
Project number
3257
Site inspections
2

Schedule

Between August 2024 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2053, more than three months after its registered date of August 2030.

0%25%50%75%100%202520272029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 September 2026

7.5%+7.0 pts

  • Burj Azizi construction site, inspection photo 1, 3 September 2026
  • Burj Azizi construction site, inspection photo 2, 3 September 2026
  • Burj Azizi construction site, inspection photo 3, 3 September 2026
  • Burj Azizi construction site, inspection photo 4, 3 September 2026

27 August 2024

0.5%

  • Burj Azizi construction site, inspection photo 1, 27 August 2024
  • Burj Azizi construction site, inspection photo 2, 27 August 2024

All 7 site photos, by inspection date

Context

Trade Center First has 3 projects under construction, 4.4% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Burj Azizi?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Burj Azizi handover date?
The registered completion date is August 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2053. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Burj Azizi?
Burj Azizi was 7.5% built at the site inspection on 3 September 2026. The site has been inspected 2 times since August 2024. The Land Department took 7 site photos at its inspections.
Is Burj Azizi delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2030.
Who is building Burj Azizi?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Burj Azizi?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.