Azizi Amir construction progress

The registered completion date for Azizi Amir in Al Furjan is June 2027. At the last site inspection, in November 2026, it was 2.4% built. The developer is Azizi Developments.

2.4%

Built, at the site inspection of 18 November 2026

Running behind its date

Registered completion date
June 2027
Construction started
June 2025
First registered
July 2025
Community
Al Furjan
Units
104
Escrow bank
Ajman Bank
Name in Arabic
عزيزي أمير
Project number
3844
Site inspections
3

Schedule

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2026

2.4%

  • Azizi Amir construction site, inspection photo 1, 18 November 2026
  • Azizi Amir construction site, inspection photo 2, 18 November 2026
  • Azizi Amir construction site, inspection photo 3, 18 November 2026
  • Azizi Amir construction site, inspection photo 4, 18 November 2026

18 March 2026

2.4%+2.4 pts

  • Azizi Amir construction site, inspection photo 1, 18 March 2026
  • Azizi Amir construction site, inspection photo 2, 18 March 2026
  • Azizi Amir construction site, inspection photo 3, 18 March 2026
  • Azizi Amir construction site, inspection photo 4, 18 March 2026

19 June 2025

0%

  • Azizi Amir construction site, inspection photo 1, 19 June 2025
  • Azizi Amir construction site, inspection photo 2, 19 June 2025

All 13 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Amir?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Amir handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Amir?
Azizi Amir was 2.4% built at the site inspection on 18 November 2026. The site has been inspected 3 times since June 2025. The Land Department took 13 site photos at its inspections.
Is Azizi Amir delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Azizi Amir?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Amir?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.