Azizi Riviera 49 construction progress
Azizi Riviera 49 in Meydan One Community is 54% built at the Land Department inspection of August 2026. Developer Azizi Developments. Completion registered for March 2027.
54%
Built, at the Land Department site inspection of 7 August 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- October 2028
- Construction started
- March 2025
- Registered with the Land Department
- September 2025
- Developer
- Azizi Developments
- Community
- Meydan One Community
- Units
- 234
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- عزيزي ريفيرا 49
- Land Department project number
- 3613
- Land Department site inspections
- 4
Schedule
Between August 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around October 2028, more than three months after the March 2027 date registered with the Land Department.
Site inspections
7 August 2026
54%+9.0 pts
19 January 2026
45%+11 pts
18 August 2025
34%+5.3 pts
8 April 2025
29%
Context
Meydan One Community has 10 projects under construction, 77% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Riviera 49?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Riviera 49 be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around October 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Riviera 49 is built?
- 54%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 4 times since April 2025.
- Is Azizi Riviera 49 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Azizi Riviera 49?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Riviera 49?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.









.jpg&w=3840&q=75)

.jpg&w=3840&q=75)