Azizi Riviera Reve construction progress

Azizi Riviera Reve in Meydan One Community is 77% built at the Land Department inspection of July 2026. Developer Azizi Developments. Completion registered for February 2025.

77%

Built, at the Land Department site inspection of 1 July 2026

20 months past its registered completion date

Completion date (Land Department)
February 2025
Finish at recent pace
May 2027
Construction started
July 2022
Registered with the Land Department
August 2022
Units
455
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزى ريفيرا ريف
Land Department project number
2434
Land Department site inspections
10

Schedule

Azizi Riviera Reve was registered to complete in February 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around May 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 July 2026

77%+14 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 1 July 2026
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 1 July 2026
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 1 July 2026
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 1 July 2026

4 December 2025

63%+9.7 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 4 December 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 4 December 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 4 December 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 4 December 2025

11 August 2025

53%+13 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 11 August 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 11 August 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 11 August 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 11 August 2025

18 April 2025

40%+8.8 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 18 April 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 18 April 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 18 April 2025
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 18 April 2025

19 November 2024

31%+3.7 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 19 November 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 19 November 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 19 November 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 19 November 2024

3 October 2024

28%+12 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 3 October 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 3 October 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 3 October 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 3 October 2024

26 June 2024

15%+13 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 26 June 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 26 June 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 26 June 2024
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 26 June 2024

31 August 2023

2.2%+1.1 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 31 August 2023
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 31 August 2023
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 31 August 2023
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 31 August 2023

6 April 2023

1.1%+0.1 pts

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 6 April 2023
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 6 April 2023
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 6 April 2023

2 August 2022

1.0%

  • Azizi Riviera Reve construction site, Land Department inspection photo 1, 2 August 2022
  • Azizi Riviera Reve construction site, Land Department inspection photo 2, 2 August 2022
  • Azizi Riviera Reve construction site, Land Department inspection photo 3, 2 August 2022
  • Azizi Riviera Reve construction site, Land Department inspection photo 4, 2 August 2022

All 66 site photos, by inspection date

Context

Meydan One Community has 10 projects under construction, 77% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Riviera Reve?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Riviera Reve be completed?
The completion date registered with the Dubai Land Department is February 2025. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Riviera Reve is built?
77%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 10 times since August 2022.
Is Azizi Riviera Reve delayed?
Yes. Its registered completion date of February 2025 has passed and the Land Department still lists it as under construction.
Who is building Azizi Riviera Reve?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera Reve?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.