Skip to content

Raffi By Azizi construction progress

Raffi By Azizi in Al Furjan is 2.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for January 2028.

2.0%

Built, at the Land Department site inspection of 25 March 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
July 2083
Construction started
January 2025
Registered with the Land Department
April 2025
Community
Al Furjan
Units
171
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي رافي
Land Department project number
3508
Land Department site inspections
3

Schedule

Between January 2025 and March 2026 the site added about 0.1 points a month. At that rate it would finish around July 2083, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 March 2026

2.0%

  • Raffi By Azizi construction site, Land Department inspection photo 1, 25 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 2, 25 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 3, 25 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 4, 25 March 2026

18 March 2026

2.0%+2.0 pts

  • Raffi By Azizi construction site, Land Department inspection photo 1, 18 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 2, 18 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 3, 18 March 2026
  • Raffi By Azizi construction site, Land Department inspection photo 4, 18 March 2026

22 January 2025

0%

  • Raffi By Azizi construction site, Land Department inspection photo 1, 22 January 2025
  • Raffi By Azizi construction site, Land Department inspection photo 2, 22 January 2025
  • Raffi By Azizi construction site, Land Department inspection photo 3, 22 January 2025

All 11 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Raffi By Azizi?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Raffi By Azizi be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around July 2083. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Raffi By Azizi is built?
2.0%, measured at the Land Department site inspection on 25 March 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is Raffi By Azizi delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Raffi By Azizi?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Raffi By Azizi?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.