Azizi Ruby construction progress
Azizi Ruby in Jumeirah Village Circle is 3.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for January 2028.
3.0%
Built, at the Land Department site inspection of 25 March 2026
Running behind its date
- Completion date (Land Department)
- January 2028
- Finish at recent pace
- August 2063
- Construction started
- January 2025
- Registered with the Land Department
- March 2025
- Developer
- Azizi Developments
- Community
- Jumeirah Village Circle
- Units
- 264
- Escrow bank
- Al Ahli Bank of Kuwait
- Name in Arabic
- عزيزي روبي
- Land Department project number
- 3529
- Land Department site inspections
- 2
Schedule
Between January 2025 and March 2026 the site added about 0.2 points a month. At that rate it would finish around August 2063, more than three months after the January 2028 date registered with the Land Department.
Site inspections
25 March 2026
3.0%+3.0 pts
27 January 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Ruby?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Ruby be completed?
- The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around August 2063. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Ruby is built?
- 3.0%, measured at the Land Department site inspection on 25 March 2026. The Land Department engineers have inspected the site 2 times since January 2025.
- Is Azizi Ruby delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
- Who is building Azizi Ruby?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Ruby?
- Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.