Azizi Ruby construction progress

Azizi Ruby in Jumeirah Village Circle is 3.0% built at the Land Department inspection of March 2026. Developer Azizi Developments. Completion registered for January 2028.

3.0%

Built, at the Land Department site inspection of 25 March 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
August 2063
Construction started
January 2025
Registered with the Land Department
March 2025
Units
264
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
عزيزي روبي
Land Department project number
3529
Land Department site inspections
2

Schedule

Between January 2025 and March 2026 the site added about 0.2 points a month. At that rate it would finish around August 2063, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 March 2026

3.0%+3.0 pts

  • Azizi Ruby construction site, Land Department inspection photo 1, 25 March 2026
  • Azizi Ruby construction site, Land Department inspection photo 2, 25 March 2026
  • Azizi Ruby construction site, Land Department inspection photo 3, 25 March 2026
  • Azizi Ruby construction site, Land Department inspection photo 4, 25 March 2026

27 January 2025

0%

  • Azizi Ruby construction site, Land Department inspection photo 1, 27 January 2025
  • Azizi Ruby construction site, Land Department inspection photo 2, 27 January 2025
  • Azizi Ruby construction site, Land Department inspection photo 3, 27 January 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Ruby?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Ruby be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around August 2063. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Ruby is built?
3.0%, measured at the Land Department site inspection on 25 March 2026. The Land Department engineers have inspected the site 2 times since January 2025.
Is Azizi Ruby delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Azizi Ruby?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Ruby?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.